header-left
File #: 0942-2013    Version: 1
Type: Ordinance Status: Passed
File created: 4/8/2013 In control: Recreation & Parks Committee
On agenda: 4/29/2013 Final action: 5/2/2013
Title: To authorize the City Auditor to transfer $59,750.00 within the voted Recreation and Parks Bond Fund 702; to amend the 2013 Capital Improvements Budget Ordinance 0645-2013; to authorize and direct the Director of Recreation and Parks to enter into contract with Jamison Well Drilling, Inc. for the Deaf School Well Improvements Project; to authorize the expenditure of $49,750.00 and a contingency of $10,000.00 for a total of $59,750.00 from the voted Recreation and Parks Bond Fund; and to declare an emergency. ($59,750.00)
Explanation
Background:
Bids were received by the Recreation and Parks Department on April 2, 2013 for the Deaf School Well Improvements Project as follows:
Status Bid Amount
Jamison Well Drilling MAJ $49,750.00
Beinhower Bros. Drilling MAJ $61,232.00

The work for which proposals are invited consists of: installing a new water well, running electrical lines, and water lines and other such work as may be necessary to complete the contract in accordance with the plans and specifications set forth in the Bid Submittal Documents. Planning Areas: 18
Principal Parties:
Jamison Well Drilling, Inc.
Tim Golden (Contact)
258 Central Ave.
Mansfield, OH 44905
419-524-8560 (Phone)
34-1636924 (Contract Compliance)

Fiscal Impact:
$59,750.00

Title
To authorize the City Auditor to transfer $59,750.00 within the voted Recreation and Parks Bond Fund 702; to amend the 2013 Capital Improvements Budget Ordinance 0645-2013; to authorize and direct the Director of Recreation and Parks to enter into contract with Jamison Well Drilling, Inc. for the Deaf School Well Improvements Project; to authorize the expenditure of $49,750.00 and a contingency of $10,000.00 for a total of $59,750.00 from the voted Recreation and Parks Bond Fund; and to declare an emergency. ($59,750.00)

Body

WHEREAS, Bids were received by the Recreation and Parks Department on April 2, 2013 for the Deaf School Well Improvements Project and will be awarded to Jamison Well Drilling, Inc. on the basis of lowest and best responsive bidder; and

WHEREAS, funds are being moved to alternate projects within Fund 702 to establish correct funding project detail location for the future project; and

WHEREAS, the 2013 Capital Improvement Budget will be amended to reflect the fund transfers from projects within Fund 702 for the Deaf School Well Improvements Project; and

WHEREAS, an emergency exists in the usual daily operation of the Recreation and Parks Department in that it is immediately n...