header-left
File #: 1681-2010    Version: 1
Type: Ordinance Status: Passed
File created: 11/15/2010 In control: Recreation & Parks Committee
On agenda: 12/6/2010 Final action: 12/9/2010
Title: To authorize and direct the Director of Recreation and Parks to enter into contract with Jess Howard Electric Company for the Electrical Improvements 2010 Project; to authorize the expenditure of $305,000.00 from the Voted Recreation and Parks Bond Fund; and to declare an emergency. ($305,000.00)
Date Ver.Action ByActionResultAction DetailsMeeting Details
12/9/20101 CITY CLERK Attest  Action details Meeting details
12/7/20101 MAYOR Signed  Action details Meeting details
12/6/20101 Columbus City Council ApprovedPass Action details Meeting details
12/6/20101 COUNCIL PRESIDENT Signed  Action details Meeting details
11/23/20101 Auditor Reviewer Reviewed and Approved  Action details Meeting details
11/23/20101 CITY AUDITOR Reviewed and Approved  Action details Meeting details
11/23/20101 Rec & Parks Drafter Sent for Approval  Action details Meeting details
11/23/20101 CITY ATTORNEY Reviewed and Approved  Action details Meeting details
11/23/20101 Rec & Parks Drafter Sent to Clerk's Office for Council  Action details Meeting details
11/22/20101 Finance Reviewer Reviewed and Approved  Action details Meeting details
11/22/20101 Finance Reviewer Reviewed and Approved  Action details Meeting details
11/22/20101 FINANCE DIRECTOR Reviewed and Approved  Action details Meeting details
11/22/20101 Rec & Parks Drafter Sent for Approval  Action details Meeting details
11/19/20101 Finance Reviewer Reviewed and Approved  Action details Meeting details
11/17/20101 Rec & Parks Drafter Sent for Approval  Action details Meeting details
11/16/20101 Rec & Parks Drafter Sent for Approval  Action details Meeting details
11/16/20101 EBOCO Reviewer Sent for Approval  Action details Meeting details
11/16/20101 ODI DIRECTOR Reviewed and Approved  Action details Meeting details
11/15/20101 Rec & Parks Drafter Sent for Approval  Action details Meeting details
11/15/20101 REC & PARKS DIRECTOR Reviewed and Approved  Action details Meeting details
Explanation

Background:
Bids were received by the Recreation and Parks Department on October 26, 2010 for the Plumbing & Electrical Improvements 2010 Project as follows:
Status Base Bid Amount
Jess Howard MAJ $275,447.00
The Waterworks MAJ Only bid plumbing portion

Since there were only a total of two bidders and one bid only the plumbing portion and the other only bid on the electric portion, we have decided to award two separate contracts.

The electrical portion of the work consists of:
Carriage Place Recreation Center: Parking Lot - Replace and relocate lights/poles currently located in middle of parking lot, and replace the existing exit light system at the recreation center.

Feddersen Recreation Center: Replace and upgrade electrical service to a 2,000 amp service panel, replace switch gears, and remove the hydronic baseboard heater.

Westgate Recreation Center: Replace and upgrade electrical service to a 2,000 amp service panel, replace switch gear, and repair/replace exterior main drain line.

The Contract Compliance Number for Jess Howard Electric Company is #31-4405752.
Contract compliant through: 1/16/2011

Emergency justification:
An emergency exists in the usual daily operations of the Recreation and Parks Department in that it is immediately necessary to enter into said contract in order to begin this work as soon as possible, thereby preserving the public health, safety and welfare of the public.

Financial Impact:
$305,000.00

Title
To authorize and direct the Director of Recreation and Parks to enter into contract with Jess Howard Electric Company for the Electrical Improvements 2010 Project; to authorize the expenditure of $305,000.00 from the Voted Recreation and Parks Bond Fund; and to declare an emergency. ($305,000.00)


Body

WHEREAS, bids were received by the Recreation and Parks Department on October 26, 2010, and the contract will be awarded on t...

Click here for full text