Explanation
1. BACKGROUND:
This legislation authorizes the Director of Public Utilities to modify the construction contract with PAE and Associates, Inc. for the purpose of providing funding for unanticipated, additional work that is required for the successful completion of the Southerly Wastewater Treatment Plant Replacement (SWWTP) of Primary Clarifier Mechanisms Project.
The purpose of the original contract was to provide for the replacement of mechanical equipment for the eight in-ground primary clarifying concrete tanks at the Southerly WWTP. It was discovered during the course of the work that additional concrete replacement is necessarywas necessary. The first tanks to be repaired have required substantially more concrete repair than was anticipated. Existing guide rails for the tanks' collector blades have been found to be in deteriorated condition and in need of replacement. Electrical components, conduit and wiring that provide power, lighting and service receptacles at each of the eight primary tanks are in deteriorated condition and need replacement as well.
2. CONSTRUCTION CONTRACT MODIFICATION:
The amount of this modification is $704,230.00, for a new amended contract total of $3,375,130.00. The modification will also extend the duration of the contract an additional 60 days to provide for this work. This legislation also provides for amending the 2003 Capital Improvements Budget.
3. EMERGENCY DESIGNATION:
The Division of Sewerage and Drainage is requesting Council to pass this ordinance as an emergency measure which is required to allow for the continuation of this project work that is necessary to allow for the rehabilitation of this vital wastewater treatment infrastructure. Failure to immediately proceed with this continued work may cause the to delay
Title
To authorize the Director of Public Utilities to modify the construction contract with PAE and Associates, Inc., for the Southerly Wastewater Treatment Plant Re...