Legislation Details

File #: 2186-2026    Version: 1
Type: Ordinance Status: First Reading
File created: 7/30/2026 In control: Public Utilities & Sustainability Committee
On agenda: 8/24/2026 Final action:
Title: To authorize the Director of Columbus Water & Power to enter into a professional services contract with Resource International, Inc. for the Cherry Hill Drive Area Water Line Improvements project; to authorize an amendment to the 2025 Capital Improvement Budget; to authorize the Director of Columbus Water & Power to apply for and accept a loan from the Ohio Water Development Authority Direct Loan Program for the Cherry Hill Drive Area Water Line Improvements project; to appropriate funds within the Water - Fresh Water Market Rate Fund; to make this ordinance contingent upon approval of a loan from the Ohio Water Development Authority; and to authorize the expenditure of up to $455,320.67 from the Water - Fresh Water Market Rate Fund. ($455,320.67)
Indexes: MBE Participation
Attachments: 1. ORD 2186-2026 2A-1 Utilization form, 2. ORD 2186-2026 SOS Resource, 3. ORD 2186-2026 Accounting Template
Date Ver.Action ByActionResultAction DetailsMeeting Details
No records to display.
Explanation
1. BACKGROUND
This ordinance authorizes the Director of Columbus Water & Power to enter into a professional services contract through the City’s RFP process with Resource International, Inc. for the Cherry Hill Drive Area Water Line Improvements Project, CIP 690236-100182, in an amount up to $455,320.67.

The purpose of this project is to construct necessary improvements to the water distribution system in the Cherry Hill Drive Area. The improvements identified in the scope of work will replace or rehabilitate water lines that have high break histories and require frequent maintenance. This project includes replacing or rehabilitating approximately 10,260 linear feet of 2-inch, 6-inch, 8-inch, and 12-inch water lines, transferring existing services, and replacing private lead service lines. The streets include Red Coach Lane, Weskit Drive (North), Boor Avenue, Weskit Drive (south), Kings Charter Road, Olde Orchard Court, Harvest Lane Court, McNaughten Road, Cherry Hill Drive, Chinaberry Drive, 2nd Alley North of Effingham Road, Cummington Court, Cummington Road, Cummington Place, and Old Farm Court.

This project is located within the following Community Planning Area: 58-Far East

TIMELINE: The duration of the design phase for this project is 14 months. It is estimated that the end of this agreement will occur in February 2028.

ESTIMATED COST OF PROJECT: The negotiated amount and proposed award amount is $455,320.67, including a 10% construction contingency amount that will be utilized to fund needed and approved changes in the work. No contract modifications are anticipated at this time; however, design exigency might later compel modification of this contract, if unforeseen difficulties are encountered.

Cost summary:

Original Contract $455,320.67
Future Anticipated Needs $ 0.00
CONTRACT TOTAL $455,320.67

2. ECONOMIC IMPACT/ADVANTAGES; COMMUNITY OUTREACH; PROJECT DEVELOPMENT; ENVIRONMENTAL FACTORS/ADVANTAGES OF...