Title: To authorize the Director of Development to enter into a contract with S.G. Loewendick & Sons, Inc. to demolish all twelve structures at 5700 Shannon Rd.; to authorize the expenditure of $74,287.50 from the Housing Preservation Fund; and to declare an emergency. ($74,287.50)
Explanation

Background: This legislation authorizes the Director of the Department of Development to enter into a contract with S.G. Loewendick & Sons, Inc. (Contract Compliance No. 31-4420502, expiration date November 9, 2013) to perform asbestos abatement services and demolish two residential structures and several accessory structures located at 5700 Shannon Rd. (010-260103). Loewendick was one of five companies who responded to a Request for Proposals (SA-004529) and was selected by an evaluation committee as the company with the best proposal. Authorization is necessary to enter into a contract for up to $74,287.50, including the proposed price of $70,750.00 plus a 5% contingency. Approximately $8,500.00 of the bid amount is for asbestos abatement; the remainder is for site work, demolition, capping of the utilities, and other associated costs.

Fiscal Impact: Funds are available within Fund 782 Housing Preservation Fund for this purpose.

Emergency Justification: Emergency action is requested in order to complete the work within the timeframe for which the cost estimates were given and demolish the structures as soon as possible.

Title

To authorize the Director of Development to enter into a contract with S.G. Loewendick & Sons, Inc. to demolish all twelve structures at 5700 Shannon Rd.; to authorize the expenditure of $74,287.50 from the Housing Preservation Fund; and to declare an emergency. ($74,287.50)

Body

WHEREAS, the City of Columbus Land Bank Program owns twelve vacant structures, at 5700 Shannon Rd., parcel number 010-260103; and

WHEREAS, the structures are and must be demolished due to their deteriorated condition; and

WHEREAS, this legislation authorizes $74,287.50 for asbestos removal and demolition of these structures; and

WHEREAS, emergency action is requested in order to complete the work within the timeframe for which the cost estimates were given; and

WHEREAS, an emergency exists in the usual daily ope...