File #: 1138-2026    Version: 1
Type: Ordinance Status: First Reading
File created: 4/10/2026 In control: Public Utilities & Sustainability Committee
On agenda: 5/18/2026 Final action:
Title: To authorize the Director of Public Utilities to enter into a contract for Construction Administration and Inspection Services with Prime AE Group, Inc. for the Youngs Drive Area Water Line Improvements project and for the General Water Construction Projects; to authorize the Director of Public Utilities to apply for and accept a loan from the Ohio Water Development Authority Direct Loan Program for the Youngs Drive Area Water Line Improvements project; to appropriate funds within the Water - Fresh Water Market Rate Fund; to amend the 2025 Capital Improvement Budget; to authorize a transfer of cash and appropriation between projects within the Water Bond Fund; to authorize the expenditure of up to $918,048.94 from the Water - Fresh Water Market Rate Fund and an expenditure of up to $75,000.00 from the Water Bond Fund for the contract; and to make this ordinance contingent upon the Ohio Water Development Authority approving a loan for the project. ($993,048.94)
Attachments: 1. ORD 1138-2026 C-2383 Vicinity Map (Youngs), 2. ORD 1138-2026 Schedule 2A-1 - Utilization Reporting Form, 3. ORD 1138-2026 SOS Prime AE, 4. ORD 1138-2026 Accounting Template
Date Ver.Action ByActionResultAction DetailsMeeting Details
No records to display.
Explanation
1. BACKGROUND
This ordinance authorizes the Director of Public Utilities to enter into a contract with Prime AE Group, Inc. for construction administration/inspection services for Department of Public Utilities construction projects bid during the calendar years 2026 through 2028 as part of the Construction Administration/Construction Inspection Services 2026-2028 contracts.

Prime AE Group, Inc. will perform construction administration/inspection services for Department of Public Utilities Capital Improvement Projects that bid during the years 2026, 2027, and 2028. The contract will be modified as needed throughout the three-year period to include these projects as they go to construction. Projects are located throughout the City of Columbus.

The following are the initial projects to be assigned to the contract:

· Youngs Drive Area Water Line Improvements, CIP 690236-100155, CT No. 2383;
Planning Area = 35 - Northland; $918,048.94

· CA-CI for General Water Construction Projects, CIP 690549-100016;
Planning Area = 99 - Citywide; $75,000.00

Prime AE Group, Inc. will be assigned tasks on this contract and will ensure the work is performed to City of Columbus construction standards and specifications. Future construction projects assigned to Prime AE Group, Inc. will be added to their Construction Administration/Construction Inspection Services 2026-2028 contract as tasks, and the contract will be modified to authorize Prime AE Group, Inc. additional work and additional funding to pay for the work.

2. PROCUREMENT
The Department of Public Utilities advertised a Request for Proposals on the Vendor Services and Bonfire websites from 8/11/25 through 9/19/25 in order to solicit proposals for the Construction Administration/Construction Inspection Services 2026-2028 contracts with the intention of awarding contracts to multiple companies. Proposals were received from the following companies:

Name CC No. Exp. Date City/State Status
DLZ Ohio CC...