Title: To authorize the Director of the Department of Recreation and Parks to enter into contract with GTC for the HVAC Equipment Upgrades 2020-2022 Project; to authorize the transfer of $3,976,500.00 within the Recreation and Parks Voted Bond Fund, to authorize the amendment of the 2023 Capital Improvements Budget; and to authorize the expenditure of $3,976,500.00 from the Recreation and Parks Voted Bond Fund. ($3,976,500.00)
Indexes: MBE Participation
Attachments: 1. Legislation - HVAC Equipment Upgrades 2020-2022 - Construction - FINAL - ATTACHMENT
Explanation

Background: This ordinance authorizes the Director of the Recreation and Parks Department to enter into contract with GTC for the HVAC Equipment Upgrades 2020-2022 Project. The contract amount is $3,659,500.00, with a contingency of $315,000.00, for a total of $3,974,500.00. An additional $2,000.00 is being authorized for interdepartmental inspections and fees for a total of $3,976,500.00 being authorized by this ordinance.

The Columbus Recreation and Parks Department is responsible for the operation of 46 buildings which contain mechanical HVAC systems. These buildings include community centers, athletic complexes, golf course clubhouses, and cultural arts centers.

Many of these systems are failing and at the end of their useful life. This project will replace air handlers, boilers, condensers, furnace units, fans, ductwork, and associated systems that are identified as failure critical and in poor condition. The project will also add air conditioning units to Howard Community Center.
A summary of the work needed and locations is as follows:

Barack Community Center - Replace boxing room air handler and two condensing units.
Beatty Community Center - Replace auditorium air handler and rooftop condensing unit.
Blackburn Community Center - Replace two roof-mounted exhaust fans.
Carriage Place Community Center - Replace five classroom HVAC units and condensing units.
Cleo Dumaree Athletic Complex - Replace boiler plant.
Dodge Community Center - Clean, insulate, and jacket ductwork.
Feddersen Community Center - Replace boiler plant
Holton Community Center - Replace two electric furnaces with gas furnace and new condensing units
Howard Community Center - Replace five classroom HVAC units and condensing units, add air conditioning units to gym and auditorium
Raymond Golf Course - Replace six furnaces and condensing units
Schiller Community Center - Replace two roof-mounted exhaust fans

Vendor Bid/Proposal Submissions (ODI designation status):