Explanation
1. BACKGROUND
This ordinance authorizes The Director of Public Service to enter into a contract with the Ohio Department of Transportation (ODOT) for the Construction of the Rich Street Bridge and Second Street and improvements to the surrounding area. This project includes the following components:
Part 1 - Relocation of the existing U.S. Route 62D structure (Town Street Bridge) over the Scioto River to Civic Center Drive and Rich Street intersection (Eastern Bank). Approach roadway reconstruction at intersections with Washington Boulevard and Civic Center Drive, including 0.24 miles of Town Street and Main Street including Scioto West Bank Park improvement; and
Part 2 - Resurfacing of 0.05 miles and reconstruction of 0.14 miles of Second Street, including reconstruction of sidewalks, traffic control, waterline, sanitary sewer improvements, storm sewer construction and post construction storm water best management practices, lying within the City of Columbus; and
As part of this project approximately 0.25 miles of new bikeway will be added which will allow for a continuous bike path at the rivers edge along the west side of the river. Approximately 0.75 miles of sidewalk will be retained in compliance with the walkability and pedestrian quality of service in the downtown area. Also, 32 curb ramps will be added or retained. This project connects to the Scioto Mile project, and supports downtown festival activities, Bicentennial park, and COSI. Bioretention planters will also be installed along with street trees, and West Bank Park will be rebuilt.
2. EMERGENCY DESIGNATION
Emergency action is requested in order to meet ODOT's schedule to bid this project on January 13, 2010. In order to do this paperwork needs to be returned to ODOT by December 31, 2009. The project is scheduled to begin construction in February 2010 and end in August 2011.
3. FISCAL IMPACT
There are many components to this project including bridge constru...