Title: To authorize the Public Service Director to reimburse the Sewerage and Drainage Division for costs incurred for the installation of sidewalks and Americans with Disabilities Act (ADA)-compliant ramps on portions of Briggs Road for the Transportation Division; to authorize the expenditure of $1,400,000.00 from the 1995, 1999 Voted Streets and Highways Fund, and to declare an emergency. ($1,400,000.00)
Attachments: 1. briggs rd.jpg
Date Ver.Action ByActionResultAction DetailsMeeting Details
7/21/20041 MAYOR Signed  Action details Meeting details
7/21/20041 CITY CLERK Attest  Action details Meeting details
7/19/20041 Columbus City Council ApprovedPass Action details Meeting details
7/19/20041 COUNCIL PRESIDENT Signed  Action details Meeting details
7/13/20041 Auditor Reviewer Reviewed and Approved  Action details Meeting details
7/13/20041 CITY AUDITOR Reviewed and Approved  Action details Meeting details
7/13/20041 SERVICE DIRECTOR Sent to Clerk's Office for Council  Action details Meeting details
7/9/20041 Service Drafter Sent for Approval  Action details Meeting details
7/9/20041 CITY ATTORNEY Reviewed and Approved  Action details Meeting details
7/9/20041 SERVICE DIRECTOR Reviewed and Approved  Action details Meeting details
7/8/20041 Finance Reviewer Reviewed and Approved  Action details Meeting details
7/8/20041 FINANCE DIRECTOR Reviewed and Approved  Action details Meeting details
7/8/20041 SERVICE DIRECTOR Reviewed and Approved  Action details Meeting details
7/8/20041 CITY ATTORNEY Reviewed and Approved  Action details Meeting details
7/8/20041 EBOCO Reviewer Reviewed and Approved  Action details Meeting details
7/8/20041 ODI DIRECTOR Reviewed and Approved  Action details Meeting details
7/7/20041 SERVICE DIRECTOR Reviewed and Approved  Action details Meeting details
7/6/20041 Service Drafter Sent for Approval  Action details Meeting details
6/16/20041 Service Drafter Sent for Approval  Action details Meeting details
6/16/20041 Service Reviewer Reviewed and Approved  Action details Meeting details
6/14/20041 Service Reviewer Reviewed and ApprovedFail Action details Meeting details
6/10/20041 Service Reviewer Reviewed and DisapprovedFail Action details Meeting details
6/3/20041 Service Drafter Sent for Approval  Action details Meeting details
Explanation

This legislation authorizes reimbursement of up to $1,400,000.00 to the Public Utilities Department, Sewerage and Drainage Division (DOSD) for sidewalk and Americans with Disabilities Act (ADA)-compliant curb ramp installation associated with the ditch enclosure and storm sewer work along Briggs Road (see street limits below and attached map).

During the 2004 construction season, DOSD will let a project to perform ditch enclosure and storm work along Briggs Road from Demorest Road to a point east of CSX railroad tracks. The Transportation Division was also considering installing sidewalks and ADA-compliant curb ramps along Briggs Road to provide a pedestrian walk path for Briggs High School students. In an effort to provide these sidewalks as expeditiously as possible it was decided to include these sidewalk locations with DOSD's project. This will provide for the installation of the sidewalks to commence by the end of the year, saving the three years it would normally take the City to design and install the sidewalks if the work was undertaken separately.

The proposed sidewalks and ADA-compliant curb ramps will be located on the north side of Briggs Road between Brinker Avenue and Woodbrook Lane and on the south side of Briggs Road between Bellflower Avenue and Briggs High School.

Project managers from both divisions worked together to coordinate these two projects. The final cost of the Transportation Division's share was estimated to be $1,400,000.00. This amount is equal to what the Transportation Division would pay to have a contractor mobilize and complete the sidewalk installation work.

Fiscal Impact: The Transportation Division budgeted $1.4 million in the 2004 Capital Improvements Budget for sidewalks for the Briggs Road project. This ordinance authorizes a reimbursement of $1.4 million to the Division of Sewerage & Drainage.

Emergency action is requested so that the Division of Sewerage & Drainage can commence...