File #: 1708-2010    Version: 1
Type: Ordinance Status: Passed
File created: 11/16/2010 In control: Utilities Committee
On agenda: 12/13/2010 Final action: 12/16/2010
Title: To authorize the Director of Public Utilities to contract with and enter into a construction contract with Kenmore Construction Company, Inc. in connection with the CSO Regulator Sluice Gate Modifications Project; to authorize the appropriation, transfer, and expenditure of $2,148,200.00 from the Sewer System Reserve Fund to the Water Pollution Control Loan Fund to fund this project expenditure for the Division of Sewerage and Drainage; and declare an emergency. ($2,148,200.00).
Attachments: 1. CIP_650737_Director's Legislation Information Sheet (Revised 04-06-10).pdf, 2. Sub-Contractor WIF 650737-100000 CSO Regulator Sluice Gate.pdf
Date Ver.Action ByActionResultAction DetailsMeeting Details
12/16/20101 CITY CLERK Attest  Action details Meeting details
12/14/20101 MAYOR Signed  Action details Meeting details
12/13/20101 Columbus City Council ApprovedPass Action details Meeting details
12/13/20101 COUNCIL PRESIDENT Signed  Action details Meeting details
12/2/20101 Utilities Drafter Sent for Approval  Action details Meeting details
12/2/20101 CITY ATTORNEY Reviewed and Approved  Action details Meeting details
12/2/20101 Utilities Drafter Sent to Clerk's Office for Council  Action details Meeting details
12/1/20101 ODI DIRECTOR Reviewed and Approved  Action details Meeting details
12/1/20101 Utilities Drafter Sent for Approval  Action details Meeting details
11/30/20101 Auditor Reviewer Reviewed and Approved  Action details Meeting details
11/30/20101 CITY AUDITOR Reviewed and Approved  Action details Meeting details
11/30/20101 Utilities Drafter Sent for Approval  Action details Meeting details
11/30/20101 EBOCO Reviewer Sent for Approval  Action details Meeting details
11/29/20101 Finance Reviewer Reviewed and Approved  Action details Meeting details
11/29/20101 Finance Reviewer Reviewed and Approved  Action details Meeting details
11/29/20101 FINANCE DIRECTOR Reviewed and Approved  Action details Meeting details
11/29/20101 Utilities Drafter Sent for Approval  Action details Meeting details
11/23/20101 UTILITIES DIRECTOR Reviewed and Approved  Action details Meeting details
11/23/20101 Utilities Drafter Sent for Approval  Action details Meeting details
11/22/20101 Utilities Reviewer Reviewed and Approved  Action details Meeting details
11/22/20101 Utilities Drafter Sent for Approval  Action details Meeting details
11/18/20101 Utilities Drafter Sent for Approval  Action details Meeting details
11/18/20101 Utilities Reviewer Reviewed and Approved  Action details Meeting details
11/17/20101 Utilities Reviewer Reviewed and Approved  Action details Meeting details
11/16/20101 Utilities Drafter Sent for Approval  Action details Meeting details
Explanation

1. BACKGROUND:

A. Need. This legislation authorizes the Director of Public Utilities to enter into a construction contract with the Kenmore Construction Company, Inc in connection with the CSO Regulator Sluice Gate Modifications Project; to authorize the appropriation, transfer, and expenditure of $2,148,200.00 from the Ohio EPA Water Pollution Control Loan Fund (WPCLF) for the Division of Sewerage and Drainage.

This is a Wet Weather Management Plan project that will address the combined sewer overflow reduction requirements of the Combined Sewer Overflow Consent Order and OEPA approved Combined Sewer Long Term Control Plan - Interim (2010) Plan Update, dated March 7, 2008.

This project will address restrictions in the existing combined sewer system in preparation of the OSIS Augmentation and Relief Sewer (OARS) and reduces the SSO's from DSR-83. This project is being performed as part of the City's OEPA approved Combined Sewer Long Term Control Plan - Interim (2010) Plan Update, dated March 7, 2008. The existing sluice gates at 15 CSO regulators (Hudson, Doe, Frambes, Indianola, King, Third, First, Henry, Chestnut, Spring, Long, Broad, Liberty, Whittier, and Moler) will be removed and the orifices at 4 regulators (Broad, Long, Chestnut and Henry) will be enlarged in order to increase flow to the wastewater treatment plants. In addition, the weir at DSR-83 will be raised approximately 2.84 ft., the sludge manhole at the Whittier Street Storm Tanks will be raised 2.75 ft. and backflow prevention will be installed at manholes 0002S0072 and 0002S0073 in order to reduce overflows at DSR-83 and increase the in-line storage upstream of DSR-83.

Work must be completed within 365 days of the Notice to Proceed.

B. Procurement Information: The Division advertised for competitive bid proposals on the City of Columbus's Vendor Services website and in the City Bulletin in accordance with the provisions of Section 329.14 of Columbus City Codes...