Explanation
1. BACKGROUND: This legislation authorizes the Director of Public Utilities to enter into a construction contract with Complete General Construction Co., in the amount of $2,485,987.80; to encumber funds with the Transportation Division for inspection, testing and prevailing wage coordination services in the amount of $374,000.00; to authorize the City Auditor to transfer a total of $1,459,987.80 within the Storm Sewer Bond Fund; to amend the 2006 Capital Improvements Budget; all in connection with the Refugee Rd. Underpass Pump Station Replacement.
2. CONSTRUCTION CONTRACT AWARD: The Director of Public Utilities publicly opened three bids on June 14, 2006. Bids were received from: Complete General Construction Co. - $2,485,987.80; Nickolas M. Savko & Sons - $2,667,807.12; and George J. Igel & Co., Inc. - $2,841,242.40.
The lowest and best bid was from Complete General Construction Co. in the amount of $2,485,987.80. Their Contract Compliance Number is 31-4366382. Additional information regarding each bidder, description of work, contract timeframe and detailed amounts can be found on the attached Legislation Information Form.
3. FISCAL IMPACT: The Division is requesting an amendment to the 2006 Capital Improvements Budget for purposes of establishing sufficient budget authority for this expenditure. Additionally, this legislation includes a transfer of funds within the Storm Sewer Bonds Fund.
Title
To authorize the Director of Public Utilities to execute a construction contract with Complete General Construction Co. in the amount of $2,485,987.80; to provide for payment of inspection, material testing and related services to the Transportation Division in the amount of $374,000.00; for the Refugee Rd. Underpass Pump Station Replacement; to authorize the transfer of $1,459,987.80 within the Storm Sewer Bond Fund; to authorize an amendment to the 2006 Capital Improvements Budget; for the Division of Sewerage and Drainage;...