Explanation
1. BACKGROUND: This legislation authorizes the Director of Public Utilities to enter into a construction contract with George J. Igel & Co., Inc. for the Downspout Redirection - Clintonville 1, Weisheimer/Indian Springs Project and Lateral Lining - Clintonville 1, Weisheimer/Indian Springs Project, C.I.P 650871-110172 & 650872-110172, the work consists of redirecting downspouts from homes to discharge to the street, and lining approximately 451 sanitary service laterals via cured-in-place pipe (CIPP) technology, and other such work as may be necessary to complete the contract, in accordance with the drawings, technical specifications, and City of Columbus Construction and Material Specifications as set forth in this Invitation For Bid (IFB).
This project, Downspout Redirection - Clintonville 1, Weisheimer/Indian Springs Project, is part of a project series known as Roof Redirection - projects. The Downspout Redirect project was advertised and bid under the Downspout name. Please note - going forward these projects will be known as Roof Redirection projects. This will align the names with information utilized in CIP Online.
The Downspout Redirection project is bond funded and the Lateral Lining project has been approved for below market-rate loan financing through the Ohio Environmental Protection Agency’s Water Pollution Control Loan Fund (WPCLF) which is administered by the Ohio Water Development Authority (OWDA). Ordinance 2778-2017, passed December 4, 2017, authorizes the Director of Public Utilities to enter into a WPCLF Loan for the project. The project’s assigned WPCLF Number is CS390274-0271. Upon the loan award, which is expected on June 28, 2018, an OWDA Loan Account number will be assigned.
2. PROJECT TIMELINE: the work is to be completed within 365 calendar days after the effective date of the Notice to Proceed.
3. PROCUREMENT INFORMATION: The Division advertised for competitive bids for the subject project on the City's Vend...
Click here for full text