Title: To authorize the Public Service Director to enter into a contract for the Transportation Division with G. Marchi & Son, LLC for construction of the Collins Avenue Raised Crosswalk and King Avenue Median (SSI OTMP) project; to authorize the expenditure of $249,171.87 from the Voted 1995, 1999, 2004 Streets and Highways Fund for the Transportation Division; and to declare an emergency. ($249,171.87).
Date Ver.Action ByActionResultAction DetailsMeeting Details
7/25/20071 CITY CLERK Attest  Action details Meeting details
7/24/20071 MAYOR Signed  Action details Meeting details
7/23/20071 Columbus City Council ApprovedPass Action details Meeting details
7/23/20071 COUNCIL PRESIDENT Signed  Action details Meeting details
7/6/20071 Auditor Reviewer Reviewed and Approved  Action details Meeting details
7/6/20071 CITY AUDITOR Reviewed and Approved  Action details Meeting details
7/6/20071 Service Reviewer Sent for Approval  Action details Meeting details
7/6/20071 ODI DIRECTOR Reviewed and Approved  Action details Meeting details
7/6/20071 Service Reviewer Sent for Approval  Action details Meeting details
7/6/20071 CITY ATTORNEY Reviewed and Approved  Action details Meeting details
7/6/20071 Service Reviewer Sent to Clerk's Office for Council  Action details Meeting details
7/5/20071 Finance Reviewer Reviewed and Approved  Action details Meeting details
7/5/20071 Finance Reviewer Reviewed and Approved  Action details Meeting details
7/5/20071 FINANCE DIRECTOR Reviewed and Approved  Action details Meeting details
7/5/20071 Service Reviewer Sent for Approval  Action details Meeting details
7/3/20071 SERVICE DIRECTOR Reviewed and Approved  Action details Meeting details
6/28/20071 Service Reviewer Reviewed and Approved  Action details Meeting details
6/26/20071 Service Drafter Sent for Approval  Action details Meeting details
Explanation

Background: This legislation authorizes the City to enter into a contract in an amount up to $219,279.89 including contingency funds, for the Collins Avenue Raised Crosswalk and King Avenue Median (SSI-OTMP) project and to pay construction inspection costs up to $29,891.98. These two locations are the first of a series of traffic calming features to be installed in the area determined to be adversely impacted by the construction of the Spring Sandusky Interchange. This improvement will include a raised crosswalk on Collins Avenue just West of Neil Avenue, and median construction on King Avenue between Cannon and Battelle. The estimated Notice to Proceed date is September 10, 2007. This contractor has been given 30 days to complete the construction of the project. The project was let by the Transportation Division and was advertised in the City Bulletin, Dodge Reports, and by the Builders Exchange. Seventeen bidders/suppliers were solicited (15 majority, 2 minority) and 4 bids were received (3 majority, 1 minority) and tabulated on May 10, 2007 as follows:

G. Marchi & Son, LLC $ 199,279.89
Danbert Inc. $ 242,849.78
McDaniel's Construction * $ 265,758.55
The Righter Co., Inc $ 298,103.54

*minority bidders

Award is to be made to G. Marchi & Son, LLC, C.C#: 31-1632119 (expiring 3/12/08), as the lowest, best, most responsive and most responsible bidder.

Emergency action is requested to allow immediate expenditure of the necessary funds so that construction may begin in September 2007.

Fiscal Impact: Funding for this project is budgeted and available within the Voted 1995, 1999, 2004 Streets and Highways Fund.