File #: 1839-2004    Version: 1
Type: Ordinance Status: Passed
File created: 10/6/2004 In control: Utilities Committee
On agenda: 11/22/2004 Final action: 11/24/2004
Title: To authorize the Finance Director to modify an existing contract with ABB, Inc. for Circuit Breakers relating to the federally mandated spill prevention control and countermeasures plan for the Division of Electricity; to authorize the expenditure of $7,000.00 from the Voted 1995 and 1999 Street Lighting and Electricity Distribution Improvements Fund; and to declare an emergency. ($7,000.00)
Date Ver.Action ByActionResultAction DetailsMeeting Details
11/24/20041 MAYOR Signed  Action details Meeting details
11/24/20041 CITY CLERK Attest  Action details Meeting details
11/22/20041 Columbus City Council ApprovedPass Action details Meeting details
11/22/20041 Columbus City Council Taken from the TablePass Action details Meeting details
11/22/20041 COUNCIL PRESIDENT Signed  Action details Meeting details
11/15/20041 Columbus City Council Tabled to Certain DatePass Action details Meeting details
11/1/20041 Utilities Drafter Sent to Clerk's Office for Council  Action details Meeting details
10/27/20041 Utilities Drafter Sent for Approval  Action details Meeting details
10/27/20041 CITY ATTORNEY Reviewed and Approved  Action details Meeting details
10/26/20041 Utilities Drafter Sent for Approval  Action details Meeting details
10/26/20041 Auditor Reviewer Reviewed and Approved  Action details Meeting details
10/26/20041 CITY AUDITOR Reviewed and Approved  Action details Meeting details
10/25/20041 FINANCE DIRECTOR Reviewed and Approved  Action details Meeting details
10/22/20041 Finance Reviewer Reviewed and Approved  Action details Meeting details
10/20/20041 ODI DIRECTOR Reviewed and Approved  Action details Meeting details
10/20/20041 Utilities Drafter Sent for Approval  Action details Meeting details
10/18/20041 Utilities Drafter Sent for Approval  Action details Meeting details
10/18/20041 EBOCO Reviewer Reviewed and Approved  Action details Meeting details
10/15/20041 UTILITIES DIRECTOR Reviewed and Approved  Action details Meeting details
10/14/20041 Utilities Reviewer Reviewed and Approved  Action details Meeting details
10/14/20041 Utilities Drafter Sent for Approval  Action details Meeting details
10/14/20041 UTILITIES DIRECTOR Reviewed and Approved  Action details Meeting details
10/8/20041 Utilities Reviewer Reviewed and Approved  Action details Meeting details
10/8/20041 Utilities Drafter Sent for Approval  Action details Meeting details
10/7/20041 Utilities Drafter Sent for Approval  Action details Meeting details
Explanation

BACKGROUND: This ordinance authorizes the Finance Director to modify an existing contract with ABB, Inc. for the Division of Electricity for the purchase of circuit breakers needed to comply with the federally mandated Spill Prevention Control and Countermeasures requirements. It is necessary to modify the contract to include the cost of Items 3 and 4 of the bid proposal that were inadvertently omitted from the authorized contract dollar amount.

Amount of additional funds to be expended: $7,000.00
(Original contract amount is $755,888.70)

Reasons additional goods/services could not be foreseen: Items 3 and 4 of Solicitation SA001121, opened May 27, 2004, were for shop drawing approval and witness testing of the 69kv and 138kv circuit breakers. The cost of these items was inadvertently omitted from the contract award letter and was not included in the authorizing Ordinance 1260-2004, passed July 19, 2004.

Reason other procurement processes are not used: ABB, Inc. was awarded the original contract for the purchase of Circuit Breakers based upon the lowest bid received May 27, 2004. ABB, Inc. submitted a bid of $3,500 each for Item 3, 69kv Circuit Breaker shop drawing approval and witness testing, and Item 4, 138kv Circuit Breaker shop drawing approval and witness testing; however, these items were not included in the amount authorized. The total amount of ABB, Inc.'s bid, including these two items, is still lower than the next lowest bidder. It would not be feasible to bid these items separately as they must be awarded to the vendor manufacturing the circuit breakers.

How cost of modification was determined: The modification is based upon the amount bid in the original bid document SA001121, opened May 20, 2004.

Contract Compliance Number: 363100018

Emergency action is requested in order to meet the USEPA mandated completion date of February 18, 2005. Failure to meet this deadline could result in substantial penalt...