Explanation
Background:
A modification to Contract No. EL001276 is needed for additional professional services related to the Alum Creek Bikeway Project.
Amount of modification is $8,500.00 bringing the total modified contract cost to $306,046.03.
Additional services required are separation of plans, separation of quantities, FEMA permit, plan modifications, and new cost estimate.
The Contract Compliance Number for Jones Stuckey, Ltd. is #31-0723296.
Emergency legislation is requested as a majority of the work is complete.
Fiscal Impact:
$8,500.00 is required and budgeted in the Greenways Voted 1999/2004 Bond Fund to meet the financial obligation of this contract modification.
Title
To authorize and direct the Director of Recreation and Parks to modify the contract with Jones Stuckey, Ltd. for additional professional services related to the Alum Creek Bikeway Project, to authorize the expenditure of $8,500.00 from the Greenways Voted 1999/2004 Bond Fund, and to declare an emergency. ($8,500.00)
Body
WHEREAS, it is necessary to modify the contract with Jones Stuckey, Ltd. for professional services related to the Alum Creek Bikeway Project; and
WHEREAS, an emergency exists in the usual daily operation of the Recreation and Parks Department in that it is immediately necessary to modify said contract as a majority of this work is complete; now, therefore
BE IT ORDAINED BY THE COUNCIL OF THE CITY OF COLUMBUS:
Section 1. That the Director of Recreation and Parks be and he is hereby authorized and directed to modify Contract No. EL001276 with Jones Stuckey, Ltd. for additional professional services related to the Alum Creek Bikeway Project, in accordance with plans and specifications on file in the Recreation and Parks Department.
Section 2. That the expenditure of $8,500.00, or so much thereof as may be necessary, be and is hereby authorized from the Greenways Voted 1999/2004 Bond Fund No. 702, Dept. No. 51-01, ...
Click here for full text