Explanation
1. BACKGROUND
This ordinance authorizes the Director of Public Utilities to enter into a contract modification with Resource International, Inc., for construction administration/inspection services as part of the Construction Administration/Construction Inspection Services 2023-2025 contracts, PO384346, PO384348, PO384351.
Resource International, Inc. was awarded a contract to perform construction administration/inspection services for Department of Public Utilities Capital Improvement projects that bid during the years 2023, 2024, and 2025. The contract is modified as needed throughout the three-year contract period to include these projects as they go to construction. The construction project to be administered by Resource International, Inc. under this contract modification is Lazelle South Tank Painting Improvements, CIP No. 690477-100021 in the amount of $409,874.90.
The Community Planning Area is “32 - Far North”.
1.1. Amount of additional funds to be expended: $409,874.90
Original Contract: $540,123.70 (ORD 0200-2023; PO384346, PO384348, PO384351)
Modification #1: $99,810.09 (ORD 1912-2023; PO405218)
Modification #2: $1,200,000.00 (ORD 2722-2023: PO426442)
Modification #3: $599,643.52 (ORD 2855-2023; PO426448, PO426452)
Modification #4: $705,530.65 (ORD 3111-2023; PO429838)
Modification #5: $342,793.47 (ORD 0065-2024; PO433096)
Modification #6: $396,719.17 (ORD 0544-2024; PO444847)
Modification #7: $62,341.50 (ORD 3017-2024; PO487347)
Modification #8: $409,874.90 (Current; PO TBD)
Total $4,356,837.00