File #: 0564-2005    Version:
Type: Ordinance Status: Passed
File created: 3/11/2005 In control: Utilities Committee
On agenda: 5/23/2005 Final action: 5/25/2005
Title: To authorize the Director of Public Utilities to contract with the Lake Erie, Inc. for construction of the Southerly Wastewater Treatment Plant Electrical System Upgrade, to authorize the appropriation, transfer and expenditure of $4,610,749.50 from the Sewer System Reserve Fund to the Ohio Water Pollution Control Loan Fund; to amend the 2004 Capital Improvements Budget.; and to declare an emergency. ($4,610,749.50)
Date Ver.Action ByActionResultAction DetailsMeeting Details
5/25/20052 ACTING CITY CLERK Attest  Action details Meeting details
5/24/20052 MAYOR Signed  Action details Meeting details
5/23/20051 Columbus City Council Amended to 30 dayPass Action details Meeting details
5/23/20051 Columbus City Council Taken from the TablePass Action details Meeting details
5/23/20051 Columbus City Council Waive the 2nd ReadingPass Action details Meeting details
5/23/20051 Columbus City Council Approved as AmendedPass Action details Meeting details
5/23/20052 COUNCIL PRESIDENT Signed  Action details Meeting details
5/9/20051 Columbus City Council Tabled IndefinitelyPass Action details Meeting details
4/26/20051 CITY AUDITOR Reviewed and Approved  Action details Meeting details
4/26/20051 Utilities Drafter Sent for Approval  Action details Meeting details
4/26/20051 CITY ATTORNEY Reviewed and Approved  Action details Meeting details
4/26/20051 Utilities Drafter Sent to Clerk's Office for Council  Action details Meeting details
4/25/20051 Utilities Drafter Sent for Approval  Action details Meeting details
4/25/20051 Auditor Reviewer Contingent Within  Action details Meeting details
4/19/20051 ODI DIRECTOR Reviewed and Approved  Action details Meeting details
4/14/20051 EBOCO Reviewer Reviewed and Approved  Action details Meeting details
4/11/20051 Utilities Drafter Sent for Approval  Action details Meeting details
4/8/20051 Finance Reviewer Reviewed and Approved  Action details Meeting details
4/8/20051 FINANCE DIRECTOR Reviewed and Approved  Action details Meeting details
3/31/20051 UTILITIES DIRECTOR Reviewed and Approved  Action details Meeting details
3/31/20051 Utilities Drafter Sent for Approval  Action details Meeting details
3/30/20051 Utilities Drafter Sent for Approval  Action details Meeting details
3/30/20051 Utilities Reviewer Reviewed and Approved  Action details Meeting details
3/18/20051 UTILITIES DIRECTOR Reviewed and Disapproved  Action details Meeting details
3/14/20051 Utilities Drafter Sent for Approval  Action details Meeting details
3/14/20051 Utilities Reviewer Reviewed and Approved  Action details Meeting details
Explanation
1. BACKGROUND:
This legislation authorizes the Director of Public Utilities to enter into a contract with Lake Erie, Inc., for construction of the Southerly Wastewater Treatment Plant Electrical System Upgrade Project for the Division of Sewerage and Drainage.

This legislation also requests an amendment to the 2004 Capital Improvements Budget in order to provide sufficient budget authority for both this construction contract award and the associated professional engineering, construction, and inspection services needed during the project's construction. Authority for the professional services contract modification is being requested in companion ordinance No. 0568-2005.

The proposed construction contract provides for the replacement of electrical power control and distribution equipment in several areas of the plant that are at the end of their reliable service life; removal and disposal of electrical transformers that contain polychlorinated biphenyl (PCB) contaminated materials; rehabilitation of air-blower equipment for the aeration process; and expansion of the plant automated instrumentation and control (I&C) system.

2. CONSTRUCTION CONTRACT AWARD:
The project was advertised in the City Bulletin, and bids were received on October 6, 2004, as follows:
1. Jess Howard Electric Company Majority Firm $ 3,917,106.90
2. Lake Erie Electric, Inc. Majority Firm $ 4,700,000.00
3. Royal Electric, Inc. Majority Firm $ 4,897,765.00
4. Claypool Electric, Inc. Majority Firm $ 5,880,000.00
5. The Ryan Company Majority Firm $ 6,304,200.00

The Engineer's construction cost estimate was $4,185,579.00

3. AWARD RECOMMENDATION: A review of the bids submitted was conducted by Division engineers and the Division's design consultant, URS. Irregularities were noted in the proposal received from the low bidder, Jess Howard Electric Company. Most of the irregularities were minor and correctable. An omission on the Bid Bond prevented the Bid from ...