File #: 1577-2003    Version: 1
Type: Ordinance Status: Passed
File created: 6/10/2003 In control: Public Service & Transportation Committee
On agenda: 6/23/2003 Final action: 6/25/2003
Title: To amend the 2002 Capital Improvements Budget, to appropriate and authorize the City Auditor to transfer $7,700,797.07 from the Special Income Tax Fund to the Voted 1995, 1999 Streets and Highways Fund; to authorize the Public Service Director to enter into a contract with Nickolas Savko & Sons, Inc. for construction of the Lane Avenue Roadway Improvement project; to authorize the expenditure of $7,909,771.53 from the Voted 1995, Voted 1999 Streets and Highways Fund for the Transportation Division and to declare an emergency. ($7,909,771.53)
Date Ver.Action ByActionResultAction DetailsMeeting Details
6/25/20031 ACTING CITY CLERK Attest  Action details Meeting details
6/24/20031 MAYOR Signed  Action details Meeting details
6/23/20031 Columbus City Council ApprovedPass Action details Meeting details
6/23/20031 COUNCIL PRESIDENT Signed  Action details Meeting details
6/17/20031 Service Drafter Sent for Approval  Action details Meeting details
6/17/20031 City Clerk's Office Sent back for Clarification/Correction  Action details Meeting details
6/17/20031 Service Drafter Sent for Approval  Action details Meeting details
6/17/20031 ODI DIRECTOR Reviewed and Approved  Action details Meeting details
6/17/20031 SERVICE DIRECTOR Reviewed and Approved  Action details Meeting details
6/16/20031 Service Drafter Sent for Approval  Action details Meeting details
6/16/20031 Auditor Reviewer Contingent Within  Action details Meeting details
6/16/20031 CITY AUDITOR Reviewed and Approved  Action details Meeting details
6/16/20031 SERVICE DIRECTOR Reviewed and Approved  Action details Meeting details
6/16/20031 CITY ATTORNEY Reviewed and Approved  Action details Meeting details
6/13/20031 SERVICE DIRECTOR Reviewed and Approved  Action details Meeting details
6/13/20031 Finance Reviewer Reviewed and Disapproved  Action details Meeting details
6/13/20031 Service Drafter Sent for Approval  Action details Meeting details
6/13/20031 Finance Reviewer Reviewed and Approved  Action details Meeting details
6/13/20031 FINANCE DIRECTOR Reviewed and Approved  Action details Meeting details
6/13/20031 Finance Reviewer Reviewed and Approved  Action details Meeting details
6/11/20031 Service Drafter Sent for Approval  Action details Meeting details
6/11/20031 SERVICE DIRECTOR Reviewed and Approved  Action details Meeting details
6/10/20031 Service Drafter Sent for Approval  Action details Meeting details
6/10/20031 Service Reviewer Reviewed and Approved  Action details Meeting details
Explanation

BACKGROUND: This legislation authorizes the Public Service Director enter into a contract with Nickolas Savko & Sons for an amount up to $7,293,646.53 for the Lane Avenue Roadway Improvement project for the Transportation Division and to pay construction inspection costs up to $616,125.00. This improvement details the widening to five lanes and the construction of curb, gutters and sidewalk on Lane Avenue from the Lane Avenue bridge east to Tuller Avenue (see attached map). The project also includes a new storm sewer system, waterline replacement, mast arm signal poles, lighting and tree plantings. The Water and Sewerage and Drainage Divisions will reimburse the Transportation Division for their respective components of the project (construction of new water lines and new storm and sanitary lines, respectively). The Notice to Proceed is estimated to be issued on July 7, 2003. Project completion is estimated at 540 days. The project was advertised in the Columbus City Bulletin and Dodge Reports and by the Builders Exchange by the Transportation Division. Twenty-five contractors were solicited (23 majority, 2 minority) and five bids were received (5 majority, 0 minority) and tabulated on May 15, 2003 as follows:

Nickolas Savko & Sons, Inc. $ 7,293,646.53
Shelly and Sands, Inc. $ 7,357,140.17
Kokosing Construction Co., Inc. $ 8,002,911.30
Complete General Construction Co. $ 8,174,820.06
George J. Igel & Co., Inc. $ 8,521,895.45

Bid award will be made to Nickolas Savko & Sons, Inc., CC# 31-0907362 (expires May 13, 2006), for the lowest, best, most responsive, and most responsible bid.

FISCAL IMPACT: The Lane Avenue Roadway Improvement project is currently budgeted in the pending 2003 Capital Improvements Budget. This ordinance amends the 2002 Capital Improvements Budget and certifies funding from the Special Income...