Title: To amend the 2023 Capital Improvement budget; to authorize the transfer of funds and appropriation within the Streets and Highways Bond Fund; to authorize the Director of Public Service to enter into contract with Complete General Construction for the Misc Econ Dev - Astor Park Streetscape Phase 1 project; to authorize the expenditure of up to $2,614,337.98 from the Streets and Highways Bond Fund for the project; and to declare an emergency. ($2,614,337.98)
Indexes: WBE Participation
Attachments: 1. Ord 2757-2023 Accouting Template.pdf, 2. Ord 2757-2023 3880-E_MAP.pdf, 3. Ord 2757-2023 subcontractors.pdf
Explanation
1. BACKGROUND
This ordinance authorizes the Director of Public Service to enter into contract with Complete General Construction Company for the Misc Econ Dev - Astor Park Streetscape Phase 1 project and to provide payment for construction, construction administration and inspection services.

This project will install streetscape improvements along the north side of Nationwide Boulevard, east side of Neiland Drive, south side of Nordecke Drive and west side of Columbus Crew Way that will coincide with private development on the adjacent parcels. Improvements along these roadways will consist of buff wash concrete sidewalks with brick tree lawn, street trees in planters and grates, streetscape amenities, and irrigation, and other work as may be necessary to complete the contract in accordance with the plans and specifications set forth in the Bid Submittal Documents.

The estimated Notice to Proceed date is November 14, 2023. The project was let by the Office of Support Services through Vendor Services and Bid Express. One bid was received on September 14, 2023, and tabulated as follows:

Company Name Bid Amount City/State Majority/ODI Certification
Complete General Construction $ 2,376,670.89 Columbus, OH Majority

Award is to be made to Complete General Construction Company as the lowest responsive and responsible and best bidder for their bid of $2,376,670.89. The amount of construction administration and inspection services will be $237,667.09. The total legislated amount is $2,614,337.98.

Searches in the System for Award Management (Federal) and the Findings for Recovery list (State) produced no findings against Complete General Construction.

As part of their bid Complete General Construction has proposed the following subcontractors to work on the project:

Company Name City/State Majority/ODI Certification ...