Legislation Details

File #: 2188-2026    Version: 1
Type: Ordinance Status: First Reading
File created: 7/30/2026 In control: Public Utilities & Sustainability Committee
On agenda: 8/24/2026 Final action:
Title: To authorize the Director of Columbus Water & Power to enter into a professional services contract with Prime AE Group, Inc. for the Hilock Road Area Water Line Improvements project; to authorize an amendment to the 2025 Capital Improvement Budget; to authorize the Director of Columbus Water & Power to apply for and accept a loan from the Ohio Water Development Authority Direct Loan Program for the Hilock Road Area Water Line Improvements project; to appropriate funds within the Water - Fresh Water Market Rate Fund; to make this ordinance contingent upon approval of a loan from the Ohio Water Development Authority; and to authorize the expenditure of up to $484,186.88 from the Water - Fresh Water Market Rate Fund. ($484,186.88)
Attachments: 1. ORD 2188-2026 Accounting Template, 2. ORD 2188-2026 Schedule 2A-1 Form, 3. ORD 2188-2026 SOS Prime
Date Ver.Action ByActionResultAction DetailsMeeting Details
No records to display.
Explanation
1. BACKGROUND
This ordinance authorizes the Director of Columbus Water & Power to enter into a professional services contract through the City’s RFP process with Prime AE Group, Inc. for the Hilock Road Area Water Line Improvements Project, CIP 690236-100184, in an amount up to $484,186.88.

The purpose of this project is to construct necessary improvements to the water distribution system in the Hilock Rd Area. The improvements identified in the scope of work will replace or rehabilitate water lines that have high break histories and require frequent maintenance. This project includes replacing or rehabilitating approximately 10,890 linear feet of 2-inch, 6-inch, and 8-inch water lines, transferring existing services, and replacing private lead service lines. The streets include Bulen Ave, Watkins Road, Lockbourne Road, Hilock Road, B Avenue (North), B Avenue (South), S Avenue, Hilock Place and Hilock Court.
This project is located within the following Community Planning Area: 64 - Far South

TIMELINE: The duration of the design phase for this project is 12 months. It is estimated that the end of this agreement will occur in January 2028.

ESTIMATED COST OF PROJECT: The negotiated amount and proposed award amount is $484,186.88, including a 15% construction contingency amount that will be utilized to fund needed and approved changes in the work. No contract modifications are anticipated at this time; however, design exigency might later compel modification of this contract, if unforeseen difficulties are encountered.

Cost summary:

Original Contract $484,186.88
Future Anticipated Needs $ 0.00
CONTRACT TOTAL $484,186.88

2. ECONOMIC IMPACT/ADVANTAGES; COMMUNITY OUTREACH; PROJECT DEVELOPMENT; ENVIRONMENTAL FACTORS/ADVANTAGES OF PROJECT
The goal of this project is to replace or rehabilitate the existing water lines that have a high break frequency. Replacement of these water lines will improve water service, decrease ...