File #: 0120-2004    Version: 1
Type: Ordinance Status: Passed
File created: 1/12/2004 In control: Utilities Committee
On agenda: 3/1/2004 Final action: 3/2/2004
Title: To authorize the Director of Public Utilities to enter into contract with The Righter Company Inc and Technical Construction Specialties Inc for the Sludge Storage Tanks SS1 and SS3 Cover Replacement for the Division of Sewerage and Drainage, to authorize the expenditure of $594,434.50 from the Sewerage System Operating Fund. ($594,434.50)
Date Ver.Action ByActionResultAction DetailsMeeting Details
3/2/20041 MAYOR Signed  Action details Meeting details
3/2/20041 CITY CLERK Attest  Action details Meeting details
3/1/20041 Columbus City Council ApprovedPass Action details Meeting details
3/1/20041 COUNCIL PRESIDENT PRO-TEM Signed  Action details Meeting details
2/23/20041 Columbus City Council Read for the First Time  Action details Meeting details
2/9/20041 Utilities Drafter Sent to Clerk's Office for Council  Action details Meeting details
2/6/20041 Auditor Reviewer Reviewed and Approved  Action details Meeting details
2/6/20041 CITY AUDITOR Reviewed and Approved  Action details Meeting details
2/6/20041 Utilities Drafter Sent for Approval  Action details Meeting details
2/6/20041 CITY ATTORNEY Reviewed and Approved  Action details Meeting details
2/5/20041 ODI DIRECTOR Reviewed and Approved  Action details Meeting details
2/5/20041 Utilities Drafter Sent for Approval  Action details Meeting details
2/4/20041 EBOCO Reviewer Reviewed and Approved  Action details Meeting details
2/2/20041 Utilities Drafter Sent for Approval  Action details Meeting details
1/30/20041 UTILITIES DIRECTOR Reviewed and Approved  Action details Meeting details
1/28/20041 UTILITIES DIRECTOR Reviewed and Approved  Action details Meeting details
1/27/20041 Utilities Reviewer Reviewed and Approved  Action details Meeting details
1/12/20041 Utilities Drafter Sent for Approval  Action details Meeting details
Explanation

The purpose of this legislation is to authorize the Director of Public Utilities to enter into contract with The Righter Company Inc and Technical Construction Specialties Inc for the Sludge Storage Tanks SS1 and SS3 Cover Replacement at the Jackson Pike Wastewater Treatment Plant.

Bids were opened on November 12, 2003. Two (2) bids were received. The award of the project is being split between the two companies. The Righter Company's bid for the concrete repair was over the project estimate. They will be awarded all other phases of this project except for concrete repair. Technical Construction Specialties Inc will be awarded the concrete repair for this project. Their bid was within the project estimate. Bids were as follows:

The Righter Company Inc: $329,000.00
Technical Construction Specialties Inc $211,395.00 - Concrete Repair Only

SUPPLIERS:

The Righter Company Inc (31-0889208)
Technical Construction Specialites Inc (34-1479038)

FISCAL IMPACT $594,434.50 is budgeted and needed for this project. The amount includes contingency money.

Title
To authorize the Director of Public Utilities to enter into contract with The Righter Company Inc and Technical Construction Specialties Inc for the Sludge Storage Tanks SS1 and SS3 Cover Replacement for the Division of Sewerage and Drainage, to authorize the expenditure of $594,434.50 from the Sewerage System Operating Fund. ($594,434.50)


Body

WHEREAS, the Sludge Storage Tanks, SS1 and SS3, at the Jackson Pike Wastewater Treatment Plant have a need for the covers to be replaced, and,

WHEREAS, the Director of Public Utilities opened bids on November 12, 2003, and,

WHEREAS, the bid submitted by the Righter Company Inc. for the concrete repair phase was over the project estimate and the company is not being awarded that portion of the project, and

WHEREAS, the project is being awarded to both the Righter Company Inc for the Demolition, Cover Support Design, Site Restor...