File #: 1019-2010    Version: 1
Type: Ordinance Status: Passed
File created: 6/25/2010 In control: Utilities Committee
On agenda: 7/26/2010 Final action: 7/28/2010
Title: To authorize the Director of Public Utilities to execute a construction contract with U.S. Utility Contractor Co. for the Dublin Avenue Substation 138KV Switch Replacement for the Division of Power and Water (Power); to encumber funds for prevailing wage coordinantion services with the Design and Construction Division; and to authorize the expenditure of $173,368.00 from the Electric B.A.B.s (Build America Bonds) Fund for the Division of Power and Water (Power). ($173,368.00)
Attachments: 1. 670608-100004 Dublin Ave Substation 138KV Switch Replacement Bid Tab.pdf, 2. 670608-100004 QFF- Quality Factors Form- Updated with C-6Factor 6-19-07.pdf, 3. 670608-100004 Director's Legislation Information Sheet.pdf, 4. 670608-100004 Sub-Contractor Work Identification Form.pdf, 5. ORD 1019-2010 Map.pdf
Date Ver.Action ByActionResultAction DetailsMeeting Details
7/28/20101 CITY CLERK Attest  Action details Meeting details
7/27/20101 MAYOR Signed  Action details Meeting details
7/26/20101 Columbus City Council ApprovedPass Action details Meeting details
7/26/20101 COUNCIL PRESIDENT PRO-TEM Signed  Action details Meeting details
7/19/20101 Columbus City Council Read for the First Time  Action details Meeting details
7/8/20101 Utilities Drafter Sent to Clerk's Office for Council  Action details Meeting details
7/7/20101 CITY ATTORNEY Reviewed and Approved  Action details Meeting details
7/7/20101 Utilities Drafter Sent for Approval  Action details Meeting details
7/7/20101 EBOCO Reviewer Sent for Approval  Action details Meeting details
7/7/20101 ODI DIRECTOR Reviewed and Approved  Action details Meeting details
7/6/20101 Finance Reviewer Reviewed and Approved  Action details Meeting details
7/6/20101 FINANCE DIRECTOR Reviewed and Approved  Action details Meeting details
7/6/20101 Utilities Drafter Sent for Approval  Action details Meeting details
7/6/20101 Auditor Reviewer Reviewed and Approved  Action details Meeting details
7/6/20101 CITY AUDITOR Reviewed and Approved  Action details Meeting details
7/6/20101 Utilities Drafter Sent for Approval  Action details Meeting details
7/2/20101 Finance Reviewer Reviewed and Approved  Action details Meeting details
7/1/20101 Utilities Drafter Sent for Approval  Action details Meeting details
7/1/20101 Utilities Drafter Sent for Approval  Action details Meeting details
7/1/20101 Utilities Reviewer Reviewed and Approved  Action details Meeting details
7/1/20101 Utilities Drafter Sent for Approval  Action details Meeting details
7/1/20101 Utilities Reviewer Sent for Approval  Action details Meeting details
7/1/20101 UTILITIES DIRECTOR Reviewed and Approved  Action details Meeting details
7/1/20101 Utilities Drafter Sent for Approval  Action details Meeting details
7/1/20101 Finance Reviewer Sent for Approval  Action details Meeting details
Explanation

1. BACKGROUND: This legislation authorizes the Director of Public Utilities to enter into a construction contract with U.S. Utility Contractor Co. in the amount of $172,367.80 and to encumber funds for prevailing wage coordination services with the Design and Construction Division in the amount of $1,000.20; in connection with the Dublin Avenue Substation 138KV Switch Replacement.

2. CONSTRUCTION CONTRACT AWARD: The Director of Public Utilities publicly opened five bids on May 5, 2010. DeBra-Kuempel - $154,000.00, Thompson Electric, Inc. - $161,843.00, U.S. Utility Contractor Co. - $172,367.80, The Ryan Company - $188,377.20 and New River Electrical Corporation - $319,786.50.

The lowest and best bid was submitted by U.S. Utility Contractor Co. Their Contract Compliance Number is 34-1606689 (expires 01/19/12, FBE). The bids submitted by DeBra-Kuempel and Thompson Electric, Inc. were both determined to be non-responsive. Neither of these bids were submitted in its entirety. Additional information regarding this bidder, description of work, contract time frame and detailed amounts can be found on the attached Legislation Information Form.

3. FISCAL IMPACT: There is sufficient cash and budget authority to fund this project.

Title

To authorize the Director of Public Utilities to execute a construction contract with U.S. Utility Contractor Co. for the Dublin Avenue Substation 138KV Switch Replacement for the Division of Power and Water (Power); to encumber funds for prevailing wage coordinantion services with the Design and Construction Division; and to authorize the expenditure of $173,368.00 from the Electric B.A.B.s (Build America Bonds) Fund for the Division of Power and Water (Power). ($173,368.00)

Body

WHEREAS, five bids for the Dublin Avenue Substation 138KV Switch Replacement was received and publicly opened in the offices of the Director of Public Utilities on May 5, 2010; and

WHEREAS, U.S. Utility Contr...