Title: To appropriate funds within the Lucent Commercial TIF; to transfer funds from the Lucent Commercial TIF to the Lucent Commercial TIF Capital Fund; to appropriate funds within the Lucent Commercial TIF Capital Fund; to authorize the Director of the Department of Public Service to enter into a contract modification with Gannett Fleming Engineers & Architects in connection with the Roadway - Westbourne Avenue Extension project; to authorize the expenditure of up to $100,000.00 from the Lucent Commercial TIF Capital Fund for the project; and to declare an emergency. ($100,000.00)
Attachments: 1. Ord. 0211-2025 Accouting Template
Explanation
1. BACKGROUND
This ordinance authorizes the Director of Public Service to modify a professional services contract with Gannett Fleming Engineers & Architects to add additional funds for Roadway - Westbourne Avenue Extension project. This modification is to design Blossom Field Boulevard from Broad Street to Westbourne Avenue.
Ordinance No. 1934-2020 authorized the Director of Public Service to enter into a $500,000.00 professional services contract with Gannett Fleming Engineers & Architects for the Roadway - Westbourne Avenue Extension project. This project consists of constructing, resurfacing, widening, new curb and gutter, sidewalks, drives, storm sewer system, and a shared use path on Westbourne Avenue from approximately 600 feet west of Taylor Station Road to Blossom Field Boulevard. This project will also include a roundabout and new alignment on Corrina Drive south of the roundabout.

Ordinance 0438-2022 authorized the Director of Public Service to modify the contract in the amount of $675,000.00 to cover the remainder of the design of Phase 1.

Ordinance 2601-2023 authorized the Director of Public Service to modify the contract in the amount of $300,000.00 to create a new public street where a private street (Blossom Field Boulevard) exists from E. Broad Street to approximately 1,800 feet north of E. Broad Street.

This ordinance authorizes the Director of Public Service to modify the contract in the amount of $100,000.00 for additional design work for Blossom Field Blvd detailed design.

1.1 Amount of additional funds to be expended: $100,000.00
The original contract amount: $500,000.00 (PO241932, Ord. 1934-2020)
The total of Modification No. 1: $675,000.00 (PO315613, Ord. 0438-2022)
The total of Modification No. 2: $300,000.00 (PO417530, Ord. 2601-2023)
The total of Modification No. 3: $100,000.00 (This Ordinance)
The contract amount including all mo...