Explanation
1. BACKGROUND
This ordinance authorizes the Director of Public Utilities to enter into a contract with The Righter Co., Inc. for construction services for the East Broad Tanks Valve Replacements project, CIP #690473-100017, in an amount up to $988,540.00 and to encumber funds with the Department of Public Service for prevailing wage services in an amount up to $2,000.00, for a total expenditure of $990,540.00.
This project provides for the replacement of valves required for isolating the East Broad elevated water storage tanks, and other such work as may be necessary to complete the contract, in accordance with the drawings, technical specifications, special provisions, and City of Columbus Construction and Material specifications.
The Community Planning Area is “58 - Far East”
TIMELINE: All work shall be complete within 140 calendar days from the Notice to Proceed. The City anticipates issuing a Notice to Proceed on or about November, 2023.
ESTIMATED COST OF PROJECT: The bid amount and proposed award amount is $988,540.00, including a 15% construction contingency amount that will be utilized to fund needed and approved changes in the work. No contract modifications are anticipated at this time; however, construction exigency might later compel modification of this contract, if unforeseen difficulties are encountered.
Original Contract $988,540.00
Future Anticipated Needs $ 0.00
CONTRACT TOTAL $988,540.00
DPS Wage Rate Administration $ 2,000.00
$990,540.00
2. ECONOMIC IMPACT/ADVANTAGES; COMMUNITY OUTREACH; PROJECT DEVELOPMENT; ENVIRONMENTAL FACTORS/ADVANTAGES OF PROJECT
The goal of this project is to replace existing water main valves that are non-operational and need to be isolated to perform maintenance. Replacement of these valves will allow painting and other maintenance work to be performed ...