header-left
File #: 0930-2017    Version: 1
Type: Ordinance Status: Passed
File created: 3/31/2017 In control: Public Service & Transportation Committee
On agenda: 4/17/2017 Final action: 4/20/2017
Title: To amend the 2016 Capital Improvements Budget; to authorize the City Auditor to transfer funds within the Streets and Highways Bond Fund and the Water General Obligations Bonds Fund; to authorize the Director of Public Service to enter into contract with Complete General Construction Company and to provide for the payment of construction, construction administration, and inspection services in connection with the Short North SID-High Street Improvements Phase 1 project; to authorize expenditures up to $3,459,101.78 relative to this project; and to declare an emergency. ($3,459,101.78)
Attachments: 1. Legislation Accounting Templates w ACDI
Explanation
1. BACKGROUND:
This legislation authorizes the Director of Public Service to enter into a contract with Complete General Construction Company for the construction of the Short North SID - High Street Improvements Phase 1 project and to provide payment for construction, construction administration and inspection services.

The Public Service Department is engaged in the Short North SID - High Street Improvements Phase 1 project. Project work includes: replacing the sidewalk and curb on the west side of North High Street between Convention Center Way and Goodale Boulevard; landscaping planter beds and street trees will be installed; North High Street will be planed and overlaid; brick crosswalks will be installed at all signalized intersections; mast arms traffic signal facilities will be installed and other traffic control improvements will be implemented; street and pedestrian light fixtures will be replaced within the project limits; storm sewer inlets will be relocated to accommodate curb modifications; and the existing 12” waterline in North High Street will be replaced between Vine Street and Spruce Street.

The project was let by the Office of Support Services through Bid Express. Three bids were received on March 28 (3 majority) and tabulated as follows:

Company Name Bid Amount City/State Majority/MBE/FBE
Complete General Construction Co. $3,144,637.98 Columbus, OH Majority
Shelly and Sands $3,358,442.56 Columbus, OH Majority
Trucco Construction $3,630,166.75 Delaware, OH Majority

Award is to be made to Complete General Construction Company as the lowest, responsive, responsible and best bidder for their bid of $3,144,637.98. The amount of construction administration and inspection services will be $314,463.80. The total legislated amount is $3,459,101.78, with the Department of Public ...

Click here for full text