Explanation
BACKGROUND: The original contract for the Hap Cremean Water Plant High & Low Service Piping Coating provided for the removal and replacement of original piping coating, that has deteriorated, debonded and failed. Due to the deterioration of existing 48" pipe, the piping has to be removed and replaced to accomodate installation of the new 48" couplings. This proposed contract modification will allow the Contractor to install new piping and couplings to connect and seal properly to allow installation of the piping coating in this area. This modification provides for additional Construction services that could not be initially foreseen due to pipe conditions encountered during construction.
EMERGENCY PROVISION: Emergency legislation is being requested to provide these services concurrently with the ongoing construction contract and to finish work prior to start of summer high pumpage water usage.
CC 329.16 CONTRACT MODIFICATIONS:
1. Amount of additional funds to be expended under this modification: $96,537.00.
2. The extent of additional services could not be initially foreseen due to deterioration of existing pipe conditions encountered during construction.
3. The work under this contract modification is a continuation of work previously performed by the Contractor, therefore, no other processes were used for procurement of these services.
4. The cost of this modification is based on material and labor, and was negotiated between the Contractor and the City, as documented by the Contractor's quotation letter, and verified by the Project Engineer.
CONTRACT AMOUNT:
Original contract amount $ 1,047,684.75
Modification No.1 $ 96,537.00
New contract amount $ 1,144,221.75
FISCAL IMPACT: The last autho...