File #: 0631-2025    Version: 1
Type: Ordinance Status: Consent
File created: 2/28/2025 In control: Public Utilities & Sustainability Committee
On agenda: 4/7/2025 Final action:
Title: To authorize the Director of Public Utilities to enter into a contract modification with Resource International for the Construction Administration/Construction Inspection Services 2023-2025 contract; to authorize an amendment to the 2024 Capital Improvement Budget; to authorize a transfer of cash and appropriation within the Sanitary Bond Fund and within the Storm Bond Fund; and to expend up to $229,324.96 from the Sanitary Bond Fund and the Storm Bond Fund for this modification. ($229,324.96)
Indexes: WBE Participation
Attachments: 1. ORD 0631-2025 Accounting Template, 2. Business_Details RII
Explanation
1. BACKGROUND
This ordinance authorizes the Director of Public Utilities to enter into a contract modification with Resource International, Inc., for construction administration/inspection services as part of the Construction Administration/Construction Inspection Services 2023-2025 contract, CIP #650800-100039.

Resource International, Inc. was awarded a contract to perform construction administration/inspection services for Division of Sewerage and Drainage Capital Improvement Projects that bid during the years 2023, 2024, and 2025. The contract is modified as needed throughout the three-year contract period to include these projects as they go to construction. The construction projects to be administered by Resource International, Inc. under this contract modification are CIP #650745-100013 2021 General Construction Contract - Sanitary, and CIP #610500-100005 2021 General Construction Contract - Storm (CA/CI).

This work will primarily be performed in Community Planning Area “99 - Citywide”.

1.1. Amount of additional funds to be expended: $229,324.96
Original Contract: $540,123.70 (ORD 0200-2023; PO384346, PO384348, PO384351)
Modification #1: $99,810.09 (ORD 1912-2023; PO405218)
Modification #2: $1,200,000.00 (ORD 2722-2023: PO426442)
Modification #3: $599,643.52 (ORD 2855-2023; PO426448, PO426452)
Modification #4: $705,530.65 (ORD 3111-2023; PO429838)
Modification #5: $342,793.47 (ORD 0065-2024; PO433096)
Modification #6: $396,719.17 (ORD 0544-2024; PO444847)
Modification #7: $62,341.50 (ORD 3017-2024; PO487347)
Modification #8: $409,874.90 (TBD)
Modification #9: $229,324.96 (Current)
Total $4,586,161.96

1.2. Reasons additio...