Explanation
1. BACKGROUND:
A. Need: This legislation authorizes the Director of Public Utilities to enter into a professional engineering services agreement with MS Consultants, Inc., for the Cherry St./Fourth St. Inflow Redirection Project for the Division of Sewerage and Drainage. The Division has determined that these services cannot be performed by City personnel at this time, and has planned for the procurement of these services on a routine basis.
This work will include preparation of construction documents (plans and specifications) for stormwater, sanitary sewer, and combined system improvements, preparation of necessary easements, and fielding technical questions during construction. Preparation of construction documents and easements will be completed within 34 months from the Notice to Proceed date. It is anticipated that construction will begin in 2012. Engineering services will end with completion of construction.
B. Procurement Information: The Division advertised Request for Proposals (RFP's) for the subject services in the City Bulletin in accordance with the provisions of Section 329.14 of Columbus City Codes. The Division of Sewerage and Drainage received technical proposals on August 8, 2008 from the following companies:
Name C.C. No. City/State Maj/MBE/FBE
MS Consultants, Inc. 34-6546916 Columbus, OH Maj.
Brown & Caldwell 68-0442806 Columbus, OH Maj.
DLZ Ohio, Inc. 31-1268980 Columbus, OH Maj.
Stantec Consulting Services Inc. 11-2167170 Columbus, OH Maj.
R. W. Armstrong & Assoc., Inc. 35-1062227 Columbus, OH Maj.
Gresham, Smith and Partners 62-0794126 Columbus, OH Maj.
MWH Americas, Inc. 95-1878805 Columbus, OH Maj.
Ribway Engineering Group, Inc. 31-1406579 Columbus, OH MBE
Metcalf & Eddy of Ohio, Inc. 22-2581306 Columbus, OH Maj.
Pomeroy & Associates, LTD. 31-1568332 Worthington, OH Maj.
These proposals were reviewed and ranked...