Explanation
BACKGROUND: Ready-mix Concrete is required for the construction of distribution circuits from the Italian Village Substation. These distribution circuits will support and relieve demands on existing Division of Electricity facilities. The required materials will be obtained in accordance with the terms and conditions of Universal Term Contract FL002656, established by the Purchasing Office, with F.W. Sloter, Inc., in the amount of $30,000.00. Their Contract Compliance Number is 31-4405874. They do not have certified MBE/FBE status.
Emergency action is requested because of circuit capacities being nearly met, it is imperative that the work be completed as soon as possible to support the OSU Gateway project and alleviate strain on the Division of Electricity's North Substation and distribution system.
FISCAL IMPACT: There are sufficient funds available in the Voted 1995 and 1999 Street Lighting and Electricity Distribution Improvements Funds for this expenditure.
Title
To authorize the Finance and Management Director to enter into a blanket purchase order in accordance with terms and conditions of an established Universal Term Contract with F.W. Sloter, Inc. for the purchase of ready-mix concrete required for the Italian Village Substation circuits; to authorize the expenditure of $30,000.00 from the Voted Street Lighting and Electricity Distribution Improvements Fund; and to declare an emergency. ($30,000.00)
Body
WHEREAS, it is necessary to construct circuits for the Italian Village Substation to alleviate strain on the Division of Electricity's North Substation and distribution system; and
WHEREAS, the Division of Electricity requires ready-mix concrete for the construction of circuits for the Italian Village Substation; and
WHEREAS, said commodity will be purchased in accordance with terms and conditions of a Universal Term Contract established by the Purchasing Office; and
WHEREAS, an emergency exists i...