Explanation
BACKGROUND: This legislation authorizes the Director of Public Utilities to reimburse the Franklin County Engineer's Office for construction of a 30-inch water main installed along Chatterton Road, Division of Power and Water Contract Number 1105.
A 30-inch water main was installed along Chatterton Road during the Franklin County Engineer's Office construction of the road widening between Fleet Road and Dunloe Road. The Division of Power and Water had a project in design to install a water main from Noe-Bixby Road to Gender Road, along Chatterton Road. The Franklin County Engineer's Office intended to complete this project prior to the water main being installed. In order to prevent the damage of new pavement, the Franklin County Engineer's Office and the Division of Power and Water agreed to have the water main installed on the County's project.
CONTRACT COMPLIANCE: 31-6400067
FISCAL IMPACT: Funding for this project is available in the Water Build America Bonds Fund.
Title
To authorize the Director of Public Utilities to reimburse the Franklin County Engineer's Office for construction of a 30-inch water main installed along Chatterton Road; and to authorize the expenditure of $166,386.00 from the Water Works Build America Bonds Fund; for the Division of Power and Water. ($166,386.00)
Body
WHEREAS, a 30-inch water main was installed along Chatterton Road during the Franklin County Engineer's Office construction of the road widening between Fleet Road and Dunloe Road; and
WHEREAS, the Division of Power and Water had a project in design to install a water main along Chatterton Road; and
WHEREAS, the Franklin County Engineer's Office intended to complete this project prior to the water main being installed, and the the Division of Power and Water agreed to have the water main installed on the County's project; and
WHEREAS, construction of the water line was completed in October 2009 and the Division of P...
Click here for full text