Explanation
1. BACKGROUND
This ordinance authorizes the Director of Columbus Water & Power to enter into a construction contract with Harold J. Becker Company, Inc. for the Jackson Pike Water Reclamation Plant Skimmings Concentration and Sludge Control Buildings Roof Replacement project, CIP #650234-100203, in an amount up to $2,155,200.00 and to encumber funds with the Department of Public Service for prevailing wage services in an amount up to $2,000.00, for a total expenditure of $2,157,200.00.
The roof of the Sludge Control and Skimmings Buildings house which stores critical equipment for the successful operation of Jackson Pike Water Reclamation Plant is exhibiting signs of failure and requires replacement. The project will replace the roof, edge metal, and lightning protection on the Jackson Pike WRP Sludge Control and Skimmings Concentration Buildings to ensure the plant remains operational.
Planning Area - 64 Far South
TIMELINE: Contract work is required to be completed in a manner acceptable to the City within 390 days from the date that a Notice to Proceed (NTP) is given by the City.
ESTIMATED COST OF PROJECT: The bid amount and proposed award amount is $2,155,200.00 including a 20% construction contingency amount that will be utilized to fund needed and approved changes in the work. No contract modifications are anticipated at this time; however, construction exigency might later compel modification of this contract, if unforeseen difficulties are encountered.
Cost summary:
Original Contract $2,155,200.00
Prevailing Wage Charge $ 2,000.00
CONTRACT TOTAL $2,157,200.00
2. ECONOMIC IMPACT/ADVANTAGES; COMMUNITY OUTREACH; PROJECT DEVELOPMENT; ENVIRONMENTAL FACTORS/ADVANTAGES OF PROJECT
There is no expected economic impact related to this project outside the direct work associated with the roof replacement. No community outreach was completed during development of this replacement project. The entire Jackson Pike Water Reclamatio...