Explanation
1. BACKGROUND:
A. Need. This legislation authorizes the Director of Public Utilities to modify the professional engineering services agreement with CH2M Hill, Inc., for the Southerly Wastewater Treatment Plant Sludge Thickening Improvements and Additional Renovations Project. The CH2MHill, Inc. modification amount requested under this ordinance is $1,419,870.00. The contract total including this modification is $10,330,197.00. The proposed contract modification provides funding for additional Services during Construction tasks for Contract S76. The potential need for this work was foreseen as construction progressed and is therefore a continuation of the services originally included within the existing contract's scope of service. It is not deemed either feasible or reasonable to suspend work with the entity currently under contract and undertake continuation of these services with another provider. The cost of the modification is a continuation of the vendor's current pricing structure, as verified by City staff. The Division has determined that these services cannot be performed by City personnel at this time.
Amount of additional funds to be expended: $1,419,870.00
Original Contract $ 1,400,000.00
Modification No. 1 $ 2,572,000.00
Modification No. 2 $ 4,688,327.00
Modification No. 3 $ 250,000.00
Proposed Modification No. 4 $ 1,419,870.00
CURRENT PROPOSED TOTAL $10,330,197.00
Reasons additional goods/services could not be foreseen:
This Contract Modification No. 4 is a continuation of the services included within the existing contract's scope of service and was anticipated as construction progressed. The effort required for several construction-phase engineering services tasks were beyond the level originally estimated and included in the contract.
Reason other procurement processes are not used:
The funding provided by this contract modi...