Title: To authorize the Director of Public Utilities to execute a construction contract with John Eramo & Sons, Inc.; for the Charleston Avenue Drainage Improvements, Resurfacing and ADA Curb Ramps Project, to provide for payment of inspection, material testing and prevailing wage coordination services to the Division of Design and Construction; to authorize the transfer and expenditure of $2,402,404.85 within the Storm Sewer Bonds Fund for the Division of Sewerage and Drainage; to authorize the transfer and expenditure of $751,344.48 within the Streets and Highways G.O. Bonds Fund for the Division of Design and Construction; and to amend the 2010 Capital Improvements Budget. ($3,153,749.34)
Attachments: 1. ORD1547-2010Map.pdf, 2. 610742 QFF- Quality Factors Form- Updated with C-6Factor 6-19-07.pdf, 3. 610742 Bid Tabulation.pdf, 4. 610742 Sub-Contractor Work Identification Form.pdf, 5. 610742 Director's Legislation Information Sheet.pdf
Date Ver.Action ByActionResultAction DetailsMeeting Details
12/9/20101 CITY CLERK Attest  Action details Meeting details
12/7/20101 MAYOR Signed  Action details Meeting details
12/6/20101 Columbus City Council ApprovedPass Action details Meeting details
12/6/20101 COUNCIL PRESIDENT Signed  Action details Meeting details
11/22/20101 Columbus City Council Read for the First Time  Action details Meeting details
11/10/20101 CITY ATTORNEY Reviewed and Approved  Action details Meeting details
11/10/20101 Utilities Drafter Sent to Clerk's Office for Council  Action details Meeting details
11/9/20101 ODI DIRECTOR Reviewed and Approved  Action details Meeting details
11/9/20101 Utilities Drafter Sent for Approval  Action details Meeting details
11/9/20101 Auditor Reviewer Reviewed and Approved  Action details Meeting details
11/9/20101 CITY AUDITOR Reviewed and Approved  Action details Meeting details
11/9/20101 Utilities Drafter Sent for Approval  Action details Meeting details
11/8/20101 Utilities Drafter Sent for Approval  Action details Meeting details
11/8/20101 EBOCO Reviewer Sent for Approval  Action details Meeting details
11/5/20101 Finance Reviewer Reviewed and Approved  Action details Meeting details
11/5/20101 Finance Reviewer Reviewed and Approved  Action details Meeting details
11/5/20101 FINANCE DIRECTOR Reviewed and Approved  Action details Meeting details
11/4/20101 Finance Reviewer Reviewed and Approved  Action details Meeting details
11/3/20101 Utilities Drafter Sent for Approval  Action details Meeting details
11/1/20101 Utilities Drafter Sent for Approval  Action details Meeting details
11/1/20101 Service Drafter Sent for Approval  Action details Meeting details
11/1/20101 Service Reviewer Reviewed and Approved  Action details Meeting details
11/1/20101 Service Drafter Sent for Approval  Action details Meeting details
11/1/20101 SERVICE DIRECTOR Reviewed and Approved  Action details Meeting details
11/1/20101 Service Drafter Sent for Approval  Action details Meeting details
10/29/20101 UTILITIES DIRECTOR Reviewed and Approved  Action details Meeting details
10/29/20101 Utilities Drafter Sent for Approval  Action details Meeting details
10/28/20101 Utilities Reviewer Sent for Approval  Action details Meeting details
10/27/20101 Utilities Drafter Sent for Approval  Action details Meeting details
10/26/20101 Utilities Reviewer Reviewed and Approved  Action details Meeting details
10/21/20101 Utilities Reviewer Reviewed and Approved  Action details Meeting details
10/21/20101 Utilities Reviewer Reviewed and Approved  Action details Meeting details
10/20/20101 Utilities Drafter Sent for Approval  Action details Meeting details
Explanation

1. BACKGROUND: This legislation authorizes the Director of Public Utilities to enter into a construction contract with John Eramo & Sons, Inc., in the amount of $2,770,783.79; to encumber funds with the Division of Design and Construction for inspection, testing, and prevailing wage coordination services in the amount of $382,965.55; all in connection with the Charleston Avenue Drainage Improvements, Resurfacing and ADA Curb Ramps Project.

This project will mitigate street and yard flooding within the area located along High Street from Bill Moose Run to Charleston Avenue, Sunnyside Lane, Kanawha Avenue and Charleston Avenue, by constructing a storm sewer, street resurfacing and ADA curb ramp installation.

2. CONSTRUCTION CONTRACT AWARD: The Director of Public Utilities publicly opened six (6) bids on August 25, 2010. These bids were received from: John Eramo & Sons, Inc. - $2,770,783.79; Nickolas Savko & Sons, Inc. - $2,823,727.21; Double Z - $2,849,714.05; George J. Igel - $2,911,249.84; Underground Utilities - $2,911,892.98 and Complete General Construction Co. - $2,970,535.58.

The lowest and best bid was from John Eramo & Sons, Inc. for $2,770,783.79. Additional information regarding each bidder, description of work, contract timeframe, detailed amounts and sub-contractors can be found on the attached Legislation Information Form.

Contract Compliance Information: 31-0724866, expires 02/05/12, Majority

3. FISCAL IMPACT: The construction costs will be paid by the Division of Sewerage and Drainage and the Division of Design and Construction. Funding for storm sewers is available by transferring cancelled funds from finished projects within the Storm Sewer Bonds Fund. Funding for street resurfacing and ADA curb ramps is available by transferring funds within the Streets and Highways G.O. Bonds Fund. Both Divisions will amend the 2010 Capital Improvements Budget to have sufficient authority for this project. The Division ...