File #: 1861-2018    Version: 1
Type: Ordinance Status: Passed
File created: 6/22/2018 In control: Public Service & Transportation Committee
On agenda: 7/9/2018 Final action: 7/12/2018
Title: To authorize the Director of Public Service to modify an existing agreement with Norfolk Southern Corporation relative to the Arterial Street Rehabilitation - Alum Creek Drive - Frebis to Refugee project; to authorize the expenditure of up to $15,000.00 from the Streets and Highways Bond Fund; and to declare an emergency. ($15,000.00)
Attachments: 1. Ordinance 1861-2018 Accounting Codes
Explanation
1. BACKGROUND
This legislation authorizes the Director of Public Service to modify an agreement with Norfolk Southern Corporation (Norfolk Southern) relative to the construction of the Arterial Street Rehabilitation - Alum Creek Drive - Frebis to Refugee project.
The aforementioned project consists of various improvements to Alum Creek Drive from Performance Way/Refugee Road South to Frebis Avenue/Integrity Drive South for the purposes of increasing capacity, reducing delays, and improving safety. Planned improvements include pavement reconstruction and widening; addition of new pedestrian and bikeway facilities on each side of the roadway; and installation of new storm sewers; street trees, and street lighting.
Ordinance 1806-2016 authorized the execution of a construction agreement, effective September 28, 2016, between the Department of Public Service and Norfolk Southern to facilitate the widening of the existing Alum Creek Drive at-grade railroad crossing and the installation of drainage pipes under that crossing. That ordinance also authorized the expenditure of $717,929.00 to support the construction and inspection of those improvements. However, the actual and anticipated future costs incurred during the prosecution of that work are higher than originally estimated.
The purpose of this legislation is to provide additional funding in the amount of $15,000.00 to support the continuation of work necessary to complete that effort.
Original contract amount: $717,929.00 (Ordinance 1806-2016; PO121875)
Modification 1 amount: $ 15,000.00
Total contract amount including all modifications: $732,929.00

2. CONTRACT COMPLIANCE INFORMATION
Norfolk Southern currently does not have a valid contract compliance number and will be required to become contract compliant before entering into agreement with the City for the provision of requisite construction services.

3. FISCAL IMPACT
Funding in the amount of $15,000.00 is available within the S...