File #: 2679-2018    Version: 1
Type: Ordinance Status: Passed
File created: 9/21/2018 In control: Public Service & Transportation Committee
On agenda: 11/5/2018 Final action: 11/7/2018
Title: To amend the 2018 Capital Improvements Budget; to authorize the transfer of funds between projects within the Streets and Highways Bond Fund; to authorize the Director of Public Service to enter into a contract modification with Shelly & Sands in connection with the Roadway Improvements - Parsons Avenue Corridor - Livingston Avenue to Hosack Street project; to authorize the expenditure of up to $660,000.00 from the Streets and Highways Bond Fund to pay for the contract modification and construction administration and inspection; and to declare an emergency. ($660,000.00)
Attachments: 1. ORD 2679-2018 Legislation Template.pdf
Explanation
1. BACKGROUND
This legislation authorizes the Director of Public Service to modify and increase an existing contract with Shelly & Sands, Inc., for the Roadway Improvements - Parsons Avenue Corridor - Livingston Avenue to Hosack Street project and to provide payment for construction, construction administration, and construction inspection services in an amount up to $660,000.00. The contract modification amount is $600,000.00, and the amount for construction administration and inspection is $60,000.00.
Ordinance 0561-2017 authorized the Director of Public Service to enter into a contract with Shelly & Sands, Inc., for the construction of the Roadway Improvements - Parsons Avenue Corridor - Livingston Avenue to Hosack Street project and to provide for construction administration and inspection services.

The work performed to date for this project consists of signal underground work, mast arms, curb ramps, storm sewer improvements, and concrete bump outs.

The work for modification 1 will consist of the construction of two additional traffic signals at the intersections of Hosack and Parsons and Innis at Parsons, decorative bike racks, replacing dead trees throughout the corridor, constructing pedestrian crossings at the intersection of Parsons Avenue and Stewart and the intersection of Parsons Avenue at Deshler, and other such work as may be necessary to complete the contract.

The original contract amount: $4,619,829.50 (PO056345, Ord. 0561-2017)
The total of Modification No. 1: $600,000.00 (This Ordinance)
The contract amount including all modifications: $5,219,829.50

Searches in the System for Award Management (Federal) and the Findings for Recovery list (State) produced no findings against Shelly & Sands, Inc.

2. UNPLANNED MODIFICATION
This is an unplanned modification to cover the cost of unforeseen work needed for the project after construction began. This unforeseen wor...

Click here for full text