File #: 0053-2026    Version: 1
Type: Ordinance Status: Consent
File created: 12/26/2025 In control: Public Utilities & Sustainability Committee
On agenda: 2/23/2026 Final action:
Title: To authorize the Director of the Department of Public Utilities to enter into a construction contract with Harold J. Becker Company for the 910 Dublin Road Garage Roof project; to authorize an amendment to the 2025 Capital Improvement Budget; to authorize the transfer of funds and appropriation between projects in the Water Bond Fund; and to authorize the expenditure of up to $568,605.00 for the project. ($568,605.00)
Attachments: 1. ORD 0053-2026 SOS, 2. ORD 0053-2026 Utilization Reporting Form, 3. ORD 0053-2026 Accounting.pdf
Explanation
1. BACKGROUND
This ordinance authorizes the Director of Public Utilities to enter into a construction contract with Harold J. Becker Company, Inc. via the City’s Invitation For Bid process for the 910 Dublin Road Garage Roof, C.I.P. Number 690026-100015, in an amount up to $566,605.00, and to pay the Department of Public Service to perform prevailing wage services for the contract in an amount up to $2,000, for a total amount of up to $568,605.00.

Portions of the 910 Dublin Road Garage Roof are in need of repair. This project will fully replace sections of the roof identified as the most prone to water infiltration. There will also be abatement along the parapet of the north wall of asbestos.

The Community Planning Area is 99 - Citywide because the 910 Dublin Road Garage services several Columbus communities.

TIMELINE: Contract work is required to be substantially completed in a manner acceptable to the City within 240 calendar days, with final completion 360 calendar days from the date that a Notice to Proceed (NTP) is given by the City.

ESTIMATED COST OF PROJECT: The contract amount is $566,605.00, which includes a contingency amount of $73,905.00 to fund needed and approved changes in the work. No contract modifications are anticipated at this time; however, construction exigency might later compel modification of this contract if unforeseen difficulties are encountered.

Cost summary:
Original Contract $ 566,605.00
Anticipated Modifications $ 0.00
CONTRACT TOTAL $ 566,605.00
Prevailing Wage Service $ 2,000.00
TOTAL CONSTRUCTION COST $ 568,605.00

2. ECONOMIC IMPACT/ADVANTAGES; COMMUNITY OUTREACH; PROJECT DEVELOPMENT; ENVIRONMENTAL FACTORS/ADVANTAGES OF PROJECT
The current roof has developed leaks and is too extensive to repair with general maintenance activities. This project will preserve the integrity of the underlying structure and stop leakage before it causes damage to interior spaces or i...