header-left
File #: 2521-2013    Version: 1
Type: Ordinance Status: Passed
File created: 10/22/2013 In control: Public Utilities Committee
On agenda: 11/18/2013 Final action: 11/20/2013
Title: To authorize the Director of Public Utilities to enter into a modification of the Specialty Maintenance Crafts Services contract with The Righter Company, Inc., for the Department of Public Utilities, to authorize the expenditure of $153,800.00 from the Sewerage System Operating Fund and $20,000.00 from the Water Operating Fund, and to declare an emergency. ($173,800.00)
Attachments: 1. ORD 2521-2013 Speciality Maint Crafts Serv. - FEM 0101.4 - Mod #6, 2. ORD 2521-2013 Speciality Maint Crafts Mod #6-Sub Work ID Form
Explanation

The Director of Public Utilities entered into a contract with The Righter Company, Inc. to provide Specialty Maintenance Crafts for various Divisions of the Department of Public Utilities, FEM Project No. 0101.4. This Modification #6 is to add additional funding for repairs at various locations of the Division of Sewerage and Drainage and the Division of Water.

The Department of Public Utilities advertised Request for Proposals (RFP's) for the subject services in the City Bulletin in accordance with the provisions of Section 329 (SA004059). Seventy one (71) vendors (62 MAJ, 9 MBE, 0 FBE) were solicited and one (1) proposal (1 MAJ), from The Righter Company, Inc., was received on August 24, 2011. The proposal was reviewed based on quality and feasibility and The Righter Company, Inc. was determined to be qualified to provide the services for the Specialty Maintenance Crafts project, for which the Division Administrator has concurred. The original contract was for a period of one year with two (2) one year renewal options on a year to year basis upon mutual agreement, availability of funding and Columbus City Council approval. The Department of Public Utilities utilized the second extension option as part of Ordinance #2089-2013. This is the 3rd year of a three (3) year contract. The contract will expire on December 1, 2014.

Additional funding for the Division of Sewerage and Drainage is required to complete some previously authorized work tasks due to unforeseen issues.
1. RFP to renovate security system for the Southerly Waste Water Treatment Plant (SWWTP) did not include electrical power to the doors with panic bars. These doors require electrification to provide a mechanical means to maneuver the bar and unlatch the closing mechanism once the door is placed on the key card/ security system.
2. RFP for SWWTP Gate Operators, during field investigations of the security system it was determined that the gate operators had failed and needed to be ...