Explanation
1. BACKGROUND: This legislation authorizes the Director of Public Utilities to enter into a construction contract with Nickolas Savko & Sons, Inc., in the amount of $2,537,214.31; to encumber funds with the Transportation Division for inspection, testing and prevailing wage coordination services in the amount of $382,000.00; to authorize the City Auditor to transfer a total of $211,714.31 within the Storm Sewer Bond Fund; to amend the 2006 Capital Improvements Budget; all in connection with the Wilson Rd. Drainage Improvements Project.
2. CONSTRUCTION CONTRACT AWARD: The Director of Public Utilities publicly opened eight bids on July 19, 2006. Bids were received from: Nickolas Savko & Sons - $2,537,214.31; George J. Igel & Co. - $2,829,306.00; Double Z Construction - $2,915,382.00; Trucco Construction - $2,990,355.36; Complete General Construction - $3,236,769.00; John Eramo & Sons - $3,285,665.17; Shelly & Sands - $3,559,842.60; and Kokosing Construction - $3,804,201.60.
The lowest and best bid was from Nickolas Savko & Sons, Inc. in the amount of $2,537,214.31. Their Contract Compliance Number is 31-0907362. Additional information regarding each bidder, description of work, contract timeframe and detailed amounts can be found on the attached Legislation Information Form.
3. FISCAL IMPACT: The Division is requesting an amendment to the 2006 Capital Improvements Budget for purposes of establishing sufficient budget authority for this expenditure. Additionally, this legislation includes a transfer of funds within the Storm Sewer Bonds Fund.
Title
To authorize the Director of Public Utilities to execute a construction contract with Nickolas Savko & Sons, Inc. in the amount of $2,537,214.31; to provide for payment of inspection, material testing and related services to the Transportation Division in the amount of $382,000.00; for the Wilson Rd. Drainage Improvements Project; to authorize the transfer of $211,714.31 within ...
Click here for full text