File #: 0681-2009    Version: 1
Type: Ordinance Status: Passed
File created: 4/30/2009 In control: Utilities Committee
On agenda: 6/1/2009 Final action: 6/3/2009
Title: To authorize the Director of Public Utilities to execute a contract modification with Jay Dee-Michels-Traylor Joint Venture for the Big Walnut Augmentation/Rickenbacker Sanitary Interceptor Project (scope change) and the Big Walnut Outfall Sewer System Capacity Augmentation Project; to amend the 2008 Capital Improvements Budget; to authorize the expenditure of $5,930,308.64 within the Ohio Water Pollution Control Loan Fund for the Division of Sewerage and Drainage; and to declare an emergency. ($5,930,308.64).
Attachments: 1. BWARI CO #12.pdf, 2. BWOAS CO#12.pdf, 3. ORD0681-2009 Director's Legislation Info Sheet.pdf
Date Ver.Action ByActionResultAction DetailsMeeting Details
6/3/20091 MAYOR Signed  Action details Meeting details
6/3/20091 CITY CLERK Attest  Action details Meeting details
6/1/20091 Columbus City Council ApprovedPass Action details Meeting details
6/1/20091 COUNCIL PRESIDENT Signed  Action details Meeting details
5/22/20091 Utilities Drafter Sent to Clerk's Office for Council  Action details Meeting details
5/21/20091 CITY ATTORNEY Reviewed and Approved  Action details Meeting details
5/19/20091 Auditor Reviewer Reviewed and Approved  Action details Meeting details
5/19/20091 CITY AUDITOR Reviewed and Approved  Action details Meeting details
5/19/20091 Utilities Drafter Sent for Approval  Action details Meeting details
5/18/20091 Utilities Drafter Sent for Approval  Action details Meeting details
5/15/20091 EBOCO Reviewer Sent for Approval  Action details Meeting details
5/15/20091 ODI DIRECTOR Reviewed and Approved  Action details Meeting details
5/14/20091 Utilities Drafter Sent for Approval  Action details Meeting details
5/13/20091 UTILITIES DIRECTOR Reviewed and Approved  Action details Meeting details
5/13/20091 Utilities Drafter Sent for Approval  Action details Meeting details
5/13/20091 Finance Reviewer Reviewed and Approved  Action details Meeting details
5/13/20091 Finance Reviewer Reviewed and Approved  Action details Meeting details
5/13/20091 FINANCE DIRECTOR Reviewed and Approved  Action details Meeting details
5/12/20091 Utilities Drafter Sent for Approval  Action details Meeting details
5/12/20091 Utilities Reviewer Reviewed and Approved  Action details Meeting details
5/12/20091 Utilities Reviewer Sent for Approval  Action details Meeting details
5/11/20091 Utilities Drafter Sent for Approval  Action details Meeting details
5/11/20091 Utilities Reviewer Reviewed and Approved  Action details Meeting details
Explanation


1. BACKGROUND:

A. Need. This legislation authorizes the Director of Public Utilities to modify the construction contract with Jay Dee-Michels-Traylor Joint Venture (JDMT JV) for the Big Walnut Augmentation/Rickenbacker Sanitary Interceptor (BWARI) Project and the Big Walnut Outfall Sewer System Capacity Augmentation (BWOAS) Project. This contract modification is necessary to complete these two projects by the end of 2009 in order to comply with a state consent agreement. After a lengthy negotiation and mediation process, a settlement agreement was reached between the Contractor and City resulting in the proposed contract modification. The JDMT JV modification amount requested under this ordinance is $5,930,308.64. The contract total including this modification is $96,709,933.64. These additional monies will fund the cost of the 650430.1 contract Change Order/Modification as follows:

BWOAS-CO-012, BWOAS-RFP-034 (650430.1):
Compensation to JDMT JV for costs to complete the BWOAS project as described in the referenced RFP
Total of this modification to the JDMT JV contract is $5,930,308 and is a change order to the existing WPCLF loan.


BWARI-CO-012, BWARI- RFP-035 (650491.1):
1.) Reduction in JDMT JV BWARI contract value for non-performance of remaining work associated with specification 09900 corrosion protection liner as described in the reference RFP; 2.) Compensation to JDMT JV BWARI Contractor for any and all costs incurred in the Specification 09900 C.P.L. claim as described in the referenced RFP; 3.) Compensation to JDMT JV BWARI Contractor for costs to complete the BWARI Project as described in the referenced RFP
Total Net Amount of $5,999,725.00 is included in the JDMT JV original contract and is a change order to the existing WPCLF loan.


B. Contract Compliance No.: CCN: 320092124 | Status: Majority | Expires: May 4, 2011