Explanation
1. BACKGROUND:
A.) Need: This legislation authorizes the Director of Public Utilities to enter into a professional construction management services contract modification with H. R. Gray & Associates, Inc. for the BWARI Tunnel Project, BWOAS Tunnel Project, and Air Quality Control Facility Project. The amount requested under this modification for the H. R. Gray & Associates, Inc. construction management services contract is $399,910.00. These funds are needed to provide inspection and continue construction management services through an extended period of construction.
This work is a continuation of Construction Management services for the BWARI Tunnel Project, BWOAS Tunnel Project, and Air Quality Control Facility Project that has been ongoing under contracts with URS Corporation. The funding for the Construction Management efforts is being separated from the services performed by the Design Professional (the City is replacing URS with CPI for engineering services associated with the protective linings). The Division of Sewerage and Drainage has determined that these services cannot be performed by City personnel at this time, and has planned for the procurement of these services on a routine basis. The potential need for the work was foreseen and so stated in the original contract's explanation of legislation.
Per the recommendation of legal council, it was determined that H.R. Gray's (sub) services should be contracted directly through the City, instead of a subsidiary of the primaries contract, during dispute resolution of URS Corporation's (primary) pending legal concerns in relation to the BWARI project due to a potential contrast of interest between URS and H.R. Gray. Due to this and the need for continued work by H.R. Gray competitive bidding on H.R. Gray's original contract for this project was waived.
B.) Contract Compliance No.: 31-1050479 | Exp. Date: 1/17/2010 | MAJ
C.) Emergency Designation: No emergency desig...
Click here for full text