1. BACKGROUND
This legislation authorizes the City Attorney to expend up to an additional $1.3 Million Dollars in connection with acquiring right-of-way for the Parsons/Livingston Avenue Roadway Improvements Project.
The Department of Public Service, Division of Design and Construction is in the process of administering the subject project that will assist the private development initiative currently being undertaken by Nationwide Children's Hospital. The hospital's growth plans will retain and add significant job opportunities for the City of Columbus. The City's roadway improvement project will be constructed with American Recovery and Revitalization Act of 2009 funding.
The purpose of this public improvement project is to widen and improve Livingston Avenue from Ninth Street east to Ohio Avenue and to widen and improve Parsons Avenue from Jackson Street north to a point approximately 200 feet north of Kennedy Drive. This project includes full depth pavement replacement, installation of traffic medians and installation of upgraded tree lawns, street lighting, sidewalks and ADA compliant ramps.
The City is currently finalizing construction plans and is actively involved in right-of-way acquisition associated with this project. Ordinance 1398-2008 (AC028955) authorized the City Attorney's office, Real Estate Division, to expend $300,000.00 for preliminary acquisition related activities associated with this project. Title work and appraisal work associated with this project are complete. It is now necessary to authorize the City Attorney's Real Estate Division staff to expend an additional $1,300,000.00 for land acquisition and other costs associated with the acquisition of the rights-of-way needed for this project.
2. FISCAL IMPACT
Funding and Budget Authority have been identified and established within the 2009 Capital Improvements Budget.
3. EMERGENCY DESIGNATION