header-left
File #: 1496-2009    Version: 1
Type: Ordinance Status: Passed
File created: 10/28/2009 In control: Utilities Committee
On agenda: 12/7/2009 Final action: 12/9/2009
Title: To authorize the Director of Public Utilities to execute a construction contract with John Eramo & Sons, Inc.; for the Gibbard Avenue Area Water Line Improvements Project; for the Division of Power and Water; to provide for payment of inspection, material testing and related services to the Transportation Division; and to authorize the appropriation and expenditure of $603,714.20 within the Ohio Water Development Authority (OWDA) Fund. ($603,714.20)
Attachments: 1. ORD1496-2009 bid tab.xls, 2. ORD1496-2009 QFF.pdf, 3. ORD1496-2009 Legis. Info. Form.pdf, 4. ORD1496-2009 map.pdf, 5. ORD1496-2009 Sub-Contractor Info.pdf
Date Ver.Action ByActionResultAction DetailsMeeting Details
12/9/20091 CITY CLERK Attest  Action details Meeting details
12/8/20091 MAYOR Signed  Action details Meeting details
12/7/20091 Columbus City Council Approved  Action details Meeting details
12/7/20091 COUNCIL PRESIDENT Signed  Action details Meeting details
11/23/20091 Columbus City Council Read for the First Time  Action details Meeting details
11/11/20091 CITY ATTORNEY Reviewed and Approved  Action details Meeting details
11/11/20091 Utilities Drafter Sent to Clerk's Office for Council  Action details Meeting details
11/10/20091 Auditor Drafter Sent for Approval  Action details Meeting details
11/10/20091 Auditor Reviewer Reviewed and Approved  Action details Meeting details
11/10/20091 CITY AUDITOR Reviewed and Approved  Action details Meeting details
11/10/20091 Utilities Drafter Sent for Approval  Action details Meeting details
11/6/20091 Utilities Drafter Sent for Approval  Action details Meeting details
11/6/20091 Auditor Reviewer Reviewed and Approved  Action details Meeting details
11/6/20091 Utilities Drafter Sent for Approval  Action details Meeting details
11/5/20091 Utilities Drafter Sent for Approval  Action details Meeting details
11/5/20091 Finance Reviewer Reviewed and Approved  Action details Meeting details
11/5/20091 Finance Reviewer Reviewed and Approved  Action details Meeting details
11/5/20091 FINANCE DIRECTOR Reviewed and Approved  Action details Meeting details
11/4/20091 EBOCO Reviewer Sent for Approval  Action details Meeting details
11/4/20091 ODI DIRECTOR Reviewed and Approved  Action details Meeting details
11/3/20091 UTILITIES DIRECTOR Reviewed and Approved  Action details Meeting details
11/3/20091 Utilities Drafter Sent for Approval  Action details Meeting details
11/2/20091 Utilities Reviewer Sent for Approval  Action details Meeting details
10/30/20091 Utilities Drafter Sent for Approval  Action details Meeting details
10/30/20091 Utilities Reviewer Reviewed and Approved  Action details Meeting details
10/30/20091 Utilities Drafter Sent for Approval  Action details Meeting details
10/29/20091 Utilities Drafter Sent for Approval  Action details Meeting details
10/29/20091 Utilities Reviewer Reviewed and Approved  Action details Meeting details
10/29/20091 Utilities Drafter Sent for Approval  Action details Meeting details
10/29/20091 Utilities Reviewer Reviewed and Approved  Action details Meeting details
Explanation

1. BACKGROUND: This legislation authorizes the Director of Public Utilities to enter into a construction contract with John Eramo & Sons, Inc., in the amount of $493,451.20; to encumber funds with the Transportation Division for inspection, testing and prevailing wage coordination services in the amount of $110,263.00; for the Gibbard Avenue Area Water Line Improvements Project, Division of Power and Water Contract Number 1108. This legislation will also authorize the appropriation and expenditure of said funds from the Ohio Water Development Authority (OWDA) Fund.

Work under this project consists of the installation of approximately 2,495 feet of 6-inch and 255 feet of 2-inch water line and appurtenances located at six separate sites:

1. Construct 6" water main in Washington Ave. from Second Ave. to Starr Ave. Transfer existing taps and abandon the existing 1" water main (~300 ft.).
2. Construct 6" water main, including fire hydrants, in Ninth St. from Gibbard Ave. to the 16" water main in Fifth Avenue. Transfer existing taps & abandon the 1 1/2" water main's (~700 ft.).
3. Transfer all existing taps from the 2" water main to the 12" water main in Gray Street between Starr Avenue & Gibbard Avenue. Abandon the 2" water main.
4. Construct 2" water main in Loew Street from Gibbard Avenue to the most northerly tap. Abandon the 1 1/2" water main (~ 950 ft.).
5. Construct 6" water main in Nineteenth Street from Gibbard Avenue to the alley south of Fifth Avenue, then east in Fourth Avenue to the 16" water main in 20th Street. Transfer existing taps and abandon the 2" water main (~950 ft.).
6. Construct 6" water main in Fair Avenue from Linwood Avenue to Latta Avenue, then south in Latta Avenue to the alley south of Kutchins Place.

This project will improve flow and water quality and replace water mains that require repeated regular maintenance.

2. CONSTRUCTION CONTRACT AWARD: The Director of Public Utilities publicly op...