File #: 2107-2011    Version: 1
Type: Ordinance Status: Passed
File created: 11/16/2011 In control: Finance Committee
On agenda: 12/5/2011 Final action: 12/7/2011
Title: To amend the 2011 Capital Improvement Budget; to authorize the City Auditor to transfer $60,800.00 between projects within the Construction Management Capital Improvement Fund; to authorize the Finance and Management Director to enter into a contract on behalf of the Office of Construction Management with Central Ohio Building for interior building renovations at the Jerry Hammond Center at 1111 East Broad Street; to authorize the expenditure of $310,800.00 from the Gov'l B.A.B.S. (Build America Bonds Fund and the Construction Management Capital Improvement Fund; and to declare an emergency.  ($310,800.00)
Explanation

BACKGROUND:  As part of the City's ongoing space planning efforts to maximize the utilization and cost effectiveness of its real estate assets, it was determined that it was in the City's best interest to move the Department of Human Resources Citywide Training function from the Piedmont Building to space available in the lower level of the Jerry Hammond Center at 1111 E. Broad Street. Design services were engaged to develop the renovation plan to provide the required office areas and training rooms. Formal bids were solicited to complete the required work. This legislation authorizes the Finance and Management Director to enter into a contract on behalf of the Office of Construction Management with Central Ohio Building for interior building renovations.

Formal bids were solicited and opened on October 31, 2011 as follows (0 MBE, 0 FBE):

Central Ohio Building                   $310,800.00

Gutknecht Construction                   $313,100.00

Elford, Inc.                        $325,086.00

Altman Company                        $332,580.00

Thomas & Marker Construction Company      $334,800.00

Quandel Group                        $379,731.00

The Office of Construction Management recommends the bid award be made to the most responsive and responsible bidder, Central Ohio Building.

Emergency action is requested so the renovations may begin as soon as possible, thereby avoiding a delay in moving City employees into this building.

Central Ohio Building Contract Compliance No. 31-0814382, expiration date April 20, 2012.

Fiscal Impact:  The cost of this contract is $310,800.00.  The current unencumbered cash balance in the Gov'l B.A.B.S. (Build America Bonds) is $250,000.00.  An additional $60,800.00 will be transferred between projects within the Construction Management Capital Improvement Fund.  