Explanation
BACKGROUND: : Residual production, transportation and disposal of sludge is a continual part of the water treatment process. The lime softening sludge lagoons at the Hap Cremean Water Plant are necessary to provide storage for emergency situations, such as loss of pumping capabilities, and to allow for maintenance of basins and pumping equipment. At the start of this project, all three (3) lagoons were filled to capacity. Consequently, the integrity of the embankments around the lagoons had been compromised. This contract provides professional engineering services for geotechnical evaluation of the embankments, and for the design and preparation of contract documents for the physical removal of the sludge and improvements to the embankments. The original contract provided for engineering design for the first two phases of the sludge removal, construction administration services for the first phase of sludge removal, and geotechnical investigations. The construction work for the first phase of sludge removal has been substantially completed and the construction work for the second phase of sludge removal has been bid. This contract modification will provide for construction administration services for the second phase of sludge removal, engineering design and construction administration services for the third phase of the work which consists of embankment stabilization and earthen internal baffle construction, and additional geotechnical investigations.
CC 329.16 CONTRACT MODIFICATIONS:
1. Amount of additional funds to be expended under this modification: $850,556.01
2. The services identified to be included in this contract modification were identified in the original contract however costs for these services were not identified at that time. It was not possible to accurately estimate the costs to perform these tasks until the first phase of the work was completed.
3. The work under this contract modification is a continu...
Click here for full text