Legislation Details

File #: 1142-2026    Version: 1
Type: Ordinance Status: First Reading
File created: 4/10/2026 In control: Public Utilities & Sustainability Committee
On agenda: 5/11/2026 Final action:
Title: To authorize the Director of Public Utilities to enter into a construction contract with Complete General Construction Company for the Community Park/Maple Canyon Home Sewage Treatment System Elimination Project; to authorize an amendment to the 2025 Capital Improvement Budget; to appropriate funds within the Water Pollution Control Loan Fund; to authorize a transfer of cash and appropriation between projects within the Sanitary Bond Fund; to make this ordinance contingent upon the Ohio Water Development Authority approving a loan for this project; and to authorize the expenditure of up to $2,152,551.20 from the Water Pollution Control Loan Fund and from the Storm Bond Fund to pay for the project. ($2,152,551.20)
Indexes: MBE Participation, WBE Participation
Attachments: 1. ORD 1142-2026 SOS Complete General Construction, 2. ORD 1142-2026 Utilization form 2A-1 650895-100004, 3. ORD 1142-2026 Accounting Template
Date Ver.Action ByActionResultAction DetailsMeeting Details
No records to display.
Explanation
1. BACKGROUND
This ordinance authorizes the Director of Public Utilities to enter into a construction contract with Complete General Construction Company through the City’s Invitation for Bid process for the Community Park/Maple Canyon Home Sewage Treatment System (HSTS) Elimination Project, CIP 650895-100004, in an amount up to $2,150,551.20; and to encumber funds with the Department of Public Service for prevailing wage verification services in an amount up to $2,000.00; for a total expenditure of $2,152,551.20.

Division of Water Reclamation projects include rehabilitation of existing sewers, repair to existing sewers, construction of new sewers, and construction of green infrastructure. The majority of the projects will reduce inflow and infiltration to the City’s sanitary sewer system thus mitigating sanitary sewer overflows to basements and waterways. The new sanitary sewer extension will serve this developed area of the City of Columbus that is currently served by home sewage treatment systems. This project will provide for the construction of approximately 2,200 linear feet of sanitary sewer main and other such work as may be necessary to complete the contract, in accordance with the drawings, technical specifications, special provisions, and City of Columbus Construction and Material specifications set forth in the Invitation For Bid.

The Columbus Community is: 35-Northland.

TIMELINE: All work shall be substantially complete in a manner acceptable to the City within 180 calendar days of the Notice to Proceed. The contract will end when the work is completed and accepted by the City.

ESTIMATED COST OF PROJECT:
The bid amount and proposed award amount is $2,150,551.20, including a 20% construction contingency amount that will be utilized to fund needed and approved changes in the work. No contract modifications are anticipated at this time; however, construction exigency might later compel modification of this contract, if unfores...

Click here for full text