File #: 1771-2004    Version: 1
Type: Ordinance Status: Passed
File created: 9/28/2004 In control: Utilities Committee
On agenda: 11/1/2004 Final action: 11/4/2004
Title: To authorize the Director of Public Utilities to modify the professional engineering services contract with URS Corporation for the Big Walnut Augmentation/Rickenbacker Interceptor Sewer Project; to authorize the appropriation, transfer and expenditure of $4,198,764.00 from the Sewer System Reserve Fund to the Ohio Water Pollution Control Loan Fund; and to amend the 2004 Capital Improvements Budget; for the Division of Sewerage and Drainage, and to declare an emergency. ($4,198,764.00)
Attachments: 1. ORD1771-2004MAP1.pdf, 2. ORD1771-2004MAP2.pdf
Date Ver.Action ByActionResultAction DetailsMeeting Details
11/4/20041 ACTING CITY CLERK Attest  Action details Meeting details
11/3/20041 MAYOR Signed  Action details Meeting details
11/1/20041 Columbus City Council ApprovedPass Action details Meeting details
11/1/20041 COUNCIL PRESIDENT Signed  Action details Meeting details
10/15/20041 Utilities Drafter Sent for Approval  Action details Meeting details
10/15/20041 CITY ATTORNEY Reviewed and Approved  Action details Meeting details
10/15/20041 Utilities Drafter Sent to Clerk's Office for Council  Action details Meeting details
10/14/20041 Auditor Reviewer Reviewed and Approved  Action details Meeting details
10/14/20041 CITY AUDITOR Reviewed and Approved  Action details Meeting details
10/13/20041 Utilities Drafter Sent for Approval  Action details Meeting details
10/12/20041 EBOCO Reviewer Reviewed and Approved  Action details Meeting details
10/12/20041 ODI DIRECTOR Reviewed and Approved  Action details Meeting details
10/8/20041 Finance Reviewer Reviewed and Approved  Action details Meeting details
10/8/20041 FINANCE DIRECTOR Reviewed and Approved  Action details Meeting details
10/8/20041 Utilities Drafter Sent for Approval  Action details Meeting details
10/7/20041 UTILITIES DIRECTOR Reviewed and Approved  Action details Meeting details
10/7/20041 Utilities Drafter Sent for Approval  Action details Meeting details
10/1/20041 Utilities Reviewer Reviewed and Approved  Action details Meeting details
10/1/20041 UTILITIES DIRECTOR Reviewed and Approved  Action details Meeting details
9/29/20041 Utilities Drafter Sent for Approval  Action details Meeting details
Explanation
1. BACKGROUND:
This legislation authorizes modifying the professional engineering services contract with URS Corporation in connection with the Big Walnut Augmentation/Rickenbacker Interceptor Sewer Project.

This professional services contract was originally procured with a scope that included a multi-year renewable contract option for an entire scope of services. This provision allows the City to appropriate funds annually or on an as-needed basis depending upon the project's progress. This modification will fund services through September, 2005, and includes the engineering services during construction; materials testing; construction administration and inspection services for both Part 1 and Part 2 of the Project.

This project will construct in two parts. Part 1 will install a 168-inch diameter sanitary interceptor sewer from the Southerly Wastewater Treatment Plant to the Alum Creek Drive/State Route 317 intersection. Part 2 will construct a 144-inch diameter sanitary interceptor sewer from Alum Creek Drive/State Route 317 intersection north along Alum Creek Drive to the existing 108-inch Outfall Sewer. The included Shook Road connection will allow the removal of the Spiegel Road pump station and a 42-inch trunk sewer that will be constructed to service the Rickenbacker Port Authority and will allow for the removal of the present pump station.

2. PROFESSIONAL ENGINEERING SERVICES MOD. AWARD: This contract is a multi-year contract that allows the City to appropriate funds on an as-need basis to cover the costs of services for a 12-18 month period, and it is necessary to fulfill the schedule and funding commitments for this project. This work is a planned, continuation of the services as originally included within the existing contract's scope of service. The contract total, including this modification is $16,805,485.00. It is also projected that modifications will be required in fiscal years 2005 and 2006 based upon current pr...