Title: To authorize the Director of the Department of Public Utilities to enter into a construction contract with JLD Construction Services LLC and Travco Construction Inc. for the 2026 Water Main Repairs project; to authorize a transfer of cash and appropriation between projects within the Water Bond Fund; and to authorize the expenditure of up to $2,625,508.60 for the project; and to declare an emergency. ($2,625,508.60)
Attachments: 1. ORD 2708-2026 JLD Utilization, 2. ORD 2708-2026 Travco Utilization, 3. ORD 2708-2026 SOS JLD, 4. ORD 2708-2026 Travco Sec of State, 5. ORD 2708-2026 Accounting Template
Date Ver.Action ByActionResultAction DetailsMeeting Details
No records to display.
Explanation
1. BACKGROUND
This ordinance authorizes the Director of Columbus Water & Power to enter into construction contracts for the 2026 Water Main Repairs project, CIP No. 690521-100014, with the following companies:
· JLD Construction Services LLC, in an amount up to $1,266,578.00
· Travco Construction Inc., in an amount up to $1,354,930.60.

This ordinance also encumbers funds with the Department of Public Service for prevailing wage services in an amount of $2,000.00 for each company, for a total of $4,000.00 for the prevailing wage services.

This contract will provide the necessary labor and equipment to complete emergency repairs to water mains at various locations within the Columbus Water Distribution System on an as needed basis.

This project was bid with the following language in the bid documents “The City reserves the right to award up to two contracts to the first, and second lowest, responsive and responsible bidders if it is in the best interest of the City to do so. If multiple contracts are awarded, the contracts will run concurrently and will be non-exclusive. The City may utilize any of the contracts at the discretion of the City.” Upon review of the bids submitted the City has decided to award the two lowest bidders a contract for the project work.

The Community Planning Area is 99 - Citywide.

TIMELINE: Contract work is required to be completed in a manner acceptable to the City within 730 days from the date that a Notice to Proceed (NTP) is given by the City.

ESTIMATED COST OF PROJECT: The bid amount and proposed award amount for JLD Construction Services, LLC is $1,266,578.00, including a 10% construction contingency amount that will be utilized to fund needed and approved changes in the work. No contract modifications are anticipated at this time; however, construction exigency might later compel modification of this contract, if unforeseen difficulties are encountered.

The bid amount and proposed award amount for Travco Constr...