header-left
File #: 0759-2013    Version: 1
Type: Ordinance Status: Passed
File created: 3/15/2013 In control: Public Service & Transportation Committee
On agenda: 4/22/2013 Final action: 4/24/2013
Title: To authorize the Director of Public Service to reimburse AEP, AT&T, Columbia Gas and other utilities for utility relocation costs incurred in conjunction with the Parsons/Schottenstein Revitalization, Southern Gateway Utility Relocation project for the Development Department; to cancel two Auditor Certificates; to amend the 2013 Capital Improvement Budget; to authorize the transfer of cash between projects within the same fund; to appropriate and authorize the expenditure of up to $225,000 within the Northland and Other Acquisitions Fund 735; and to declare an emergency. ($225,000.00)
Explanation

1. BACKGROUND
Properties near the site of the former Schottenstein’s department store have been purchased by the City of Columbus over the past 5 years since the Parsons Avenue Vision Plan called for redevelopment of key properties along Parsons Avenue. Demolition of existing structures was completed in 2010.
Currently, redevelopment plans are being formulated for the entire site bounded by Innis Avenue on the north, Barthman Street on the south, Washington Avenue on the west and Parsons Avenue on the east. The first structure to be built located in the southeast quadrant of the site is the Maloney Health Center, one of a network of Neighborhood Health Centers owned by the City of Columbus.
2. CONTRACT COMPLIANCE
Columbus Southern Power Company dba American Electric Power (AEP) contract compliance number is 314271000. The expiration date for their contract compliance is 7/11/14
AT&T contract compliance number is 340436390. The expiration date for their contract compliance is 2/13/14
Columbia Gas contract compliance number is 310673990. The expiration date for their contract compliance is 3/21/15
3. FISCAL IMPACT
A portion of the funding needed for this project will be from cancelling $37,023.70 from Auditor Certificates. Full funding for this purpose is budgeted within the 2013 Capital Improvement Budget and is available in Fund 735, the Northland and Other Acquisitions bond fund.
4. EMERGENCY DESIGNATION
Emergency action is requested to provide reimbursement to these utilities at the earliest possible time for costs incurred for the relocation of utilities for the Parsons/Schottenstein Revitalization, Southern Gateway Utility Relocation project.


Title

To authorize the Director of Public Service to reimburse AEP, AT&T, Columbia Gas and other utilities for utility relocation costs incurred in conjunction with the Parsons/Schottenstein Revitalization, Southern Gateway Utility Relocation project for the Development Department; to cancel two...

Click here for full text