Explanation
BACKGROUND: Wooden Poles, Pole Line Hardware and Ready Mix Concrete are required for the construction of distribution circuits from the Italian Village Substation. These distribution circuits will support and relieve demands on existing Division of Electricity facilities. The required materials will be obtained in accordance with the terms and conditions of existing universal term contracts established by the Purchasing Office, as follows:
McFarland Cascade Holdings | CC# 911277142 | FL002237 | $32,500.00
F.W. Sloter, Inc. | CC# 314405874 | FL002656 | $58,920.00
WESCO Dist., Inc. | CC #251723345 | FL002291 | $35,000.00
Hughes Supply Inc. | CC# 370798775 | FL002289 | $15,000.00
Reed City Power Line Supply | CC# 381783949 | FL002285 | $10,000.00
Consolidated Electrical Dist. | CC# 952563864 | FL002286 | $5,000.00
Becker Electric | CC# 310553243 | FL002287 | $5,000.00
This legislation also authorizes a transfer of funds within the Voted 1995 and 1999 Street Lighting and Electricity Distribution Improvements Fund and amends the 2004 Capital Improvements Budget to reflect the transfer.
Emergency action is requested because of circuit capacities being nearly met, it is imperative that the work be completed as soon as possible to support the OSU Gateway project and alleviate strain on the Division of Electricity's North Substation and distribution system.
FISCAL IMPACT: There are sufficient funds available in the Voted 1995 and 1999 Street Lighting and Electricity Distribution Improvements Funds for this expenditure. It is necessary to transfer funds from the Distribution System Improvements project to the Italian Village Substation project and to amend the 2004 Capital Improvements Budget accordingly.
Title
To amend the 2004 Capital Improvements Budget; to transfer $161,420.00 within the Voted Street Lighting and Electricity Distribution Improvements Fund; to authorize the Finance Director to enter into blanket purchase ...
Click here for full text