Explanation
Background: This ordinance authorizes the Director of the Recreation and Parks Department to modify an existing contract with Marker, Inc. dba Marker Construction to provide construction services associated with the Marion Franklin Pool Replacement Project. The modification amount is $9,268,376.00, with an additional $10,500.00 for interdepartmental inspections and fees, for a total of $9,278,876.00 being authorized by this ordinance.
The Recreation and Parks Department is delivering this project using a Construction Manager at Risk (CMR) format and this modification will allow progress to the next phase of building this facility. The previous ordinances allowed for the design phase and pre-construction phase of the project to be completed. They also initiated the procurement of long lead time materials, including pumps, filters chemical storage systems, and electrical equipment. This portion of the project will include additional professional services and full construction of the new facility. This is a planned modification that will allow construction of the project to be completed in time for the 2026 swim season.
The original completion date of the project was May 24, 2026. The modified project completion date, as a result of the proposed modification, will remain May 24, 2026.
Amount of Additional Funds: $9,278,876.00
Why Additional Services Were Not Foreseen: This modification was foreseen due to the nature of Construction Manager at Risk contracts. This modification covers the scope for construction of the project.
Why It Is Not In The Best Interest For The City To Award Additional Services Through Another Procurement Process: All of the scope associated with this vendor's contract modification was planned as part of the original project scope. The project was broken into phases and contract modifications to align with the Construction Manager at Risk project delivery method.
How The Price For The Additional Services Was Determined: The ...